Fume hood exhaust fan process load?
NC-2009 EAp2:Minimum Energy Performanceposted by Haojie Wang on
I think fume hood exhaust are unregulated in 90.1 2007 thus should be process load. But just want to confirm. I do see EPAct 2005 says fume hood should not be treated as process load...
Basline system for 5 floors + small below grade conditioned spac
NC-2009 EAp2:Minimum Energy Performanceposted by Zonda E. Team on
What is in your opinion the baseline for the following building: Floor area:12,000 sqm (130,000 sqft) Floors: 5 above grade, mostly conditioned.
Pre-development Conditions
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Leandro Silva on
Greetings Our project is a 30 year old building undergoing a Major Renovation and will be registered as LEED-NC v2009. In calculating pre- and post-development runoff, do we consider the pre-develo
Is the credit for during construction, or after envelope is up?
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Nelina Loiselle on
We have an issue with a General Contractor on a project.
SS 4.4 No New Parking.
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Rezkar Abdulmajeed on
I have the first LEED project in a campus. The project will be built on an existing parking lot and no new parking will be added within the LEED project boundary.
Fuel Stations for Shared Parking Lot Outside of LEED Boundary
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Mary Kay on
Our project has no new parking. We are on a campus where there is an existing parking lot adjacent to our building, but not within our LEED project boundary.
Additional lighting power density in a retail store
CS-2009 EAp2:Minimum Energy Performanceposted by Felipe Duran on
Dear All, We are working on a shopping mall project which is pursuing LEED for C&S certification.
Shared building electricity meter
EBOM-v4 EAp2:Minimum energy performanceposted by LEED Pro Consultant on
We have a building which shares electricity meter with an adjacent building, only one building will be intended for certification, it is possible to identify the percentage of consumption in every
small DES
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
For a preliminary review I modeled a building that is heated and cooled by four geothermal heat pumps that are located in a technical room within the building.
Pilot Credit Closed
Pilot-Credits EApc8:Demand responseposted by Haley Duncan on
Hi, It looks like USGBC has closed this pilot credit to NC 2009 projects.