Forum » CI-2009 EAc3
Topic

Cooling Fuels

CI-2009 EAc3: Measurement and Verification
posted by Nandana Kumar on Dec 10, 2012, 12:11 am

Hi,

We need a clarification about the cooling fuels. What are cooling fuels referred to?
Thank you
Nandana

Last reply: Marcus Sheffer, Dec 11, 2012, 9:23 am

To meter or not to meter

CI-2009 EAc3: Measurement and Verification
posted by Rudolph Carneiro on Nov 12, 2012, 12:39 pm

I have a store (case 1) with a small 60 ton chiller, 2...

Last reply: Gordon Shymko, Nov 26, 2012, 11:45 am

Metering Requirements Case 1

CI-2009 EAc3: Measurement and Verification
posted by Matthew Tovar on Oct 2, 2012, 5:32 pm

For case 1 (project less than 75% of the total bldg sqft), can temporary metering fulfill the metering requirement? If so, under what circumstances (e.g. minimum monitoring period length, BMS...

Last reply: Marcus Sheffer, Oct 17, 2012, 9:34 am

M&V case 2: System required to be monitored not installed

CI-2009 EAc3: Measurement and Verification
posted by Edwin Wealend on Jun 7, 2010, 10:14 pm

Hi,

We have a project where we are converting a warehouse into an office, it will have a site area > 75% of the building area, infact the whole...

Last reply: Luis Miguel Diazgranados, Jan 30, 2012, 10:18 am

LEED project defined boundary 1.5 buildings

CI-2009 EAc3: Measurement and Verification
posted by Steve Khouw on Jun 26, 2011, 4:10 pm

Just to be sure, to be sure, not trying to be picky here. Our new LEED-CI project encompasses 2 buildings, but only 1 is going to be fully occupied and the other only partially,

Last reply: Gordon Shymko, Nov 21, 2011, 3:55 pm

M&V- energy costs paid by tenant

CI-2009 EAc3: Measurement and Verification
posted by Sarah Marvez on Aug 17, 2011, 4:10 pm

Our project occupies

Last reply: Gordon Shymko, Nov 21, 2011, 3:53 pm

M&V plan required for case 1, or not?

CI-2009 EAc3: Measurement and Verification
posted by Dave Intner on Dec 15, 2009, 6:10 pm

It seems logical that no M&V plan would be required for Case 1 as you state above. However, the reference guide (page 187) appears to clearly call for it in both cases. Our project is well...

Last reply: Gordon Shymko, Nov 21, 2011, 3:37 pm

Are Form submetering requirements greater than Ref Guide?

CI-2009 EAc3: Measurement and Verification
posted by Raphael Sperry on Sep 28, 2011, 4:19 pm

In Case 1 (project

Last reply: Ante Vulin, Oct 18, 2011, 11:44 am

Metering and Submetering

CI-2009 EAc3: Measurement and Verification
posted by Steve Khouw on Oct 20, 2010, 1:35 pm

We are still confused between the two. Correct me if I am wrong. Metering means installing an electricity (and water meter) device that record consumption for the entire project (or whole tenancy...

Last reply: Ralf Lehmann, Oct 4, 2011, 10:52 am

Case 1 Option 2

CI-2009 EAc3: Measurement and Verification
posted by breeze glazer on May 11, 2011, 12:30 pm

We have a situation where the tenant space, is within a building owned, by the owner. There essentially is no lease as they own the entire building - Is the project eligible for 3 points where...

Last reply: Gordon Shymko, May 26, 2011, 7:12 pm