Forum » CI-2009 EAc1.4
Loading...
Topic

Servers, routers, switches

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Susan Walker-Meere on Aug 11, 2013, 10:59 am

Hi, Would you clarify if routers and switches should be included in the list?

Last reply: Allen Cornett, Sep 18, 2019, 11:10 am

Gas powered equipment

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Mike D on Mar 21, 2014, 12:26 pm

Is equipment that is powered by gas (such as gas cookers, fryers, ovens) to be included in the list as well or should we just include electrical equipment?

Last reply: Michelle Rosenberger, Jan 29, 2019, 4:51 pm

Coffee Maker- Energy Star

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Chris Hocknell on Feb 27, 2012, 6:21 am

Hi all, I've got a question that I can't seem to resolve. I have a warm beverage maker specified on a project; a Flavia Creation 400, it is not Energy Star rated but I can't determine what the...

Last reply: Stacey Olson, Nov 29, 2018, 5:12 pm

Single Phase UPS

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Omar Delgado on Aug 24, 2011, 6:54 pm

Greetings all,

I have a CI project that has single phase UPS, PoE Switches, and some AiroNet AP. Are all these excluded from the calculation?

Thanks!

Last reply: Danna Richey, Nov 8, 2018, 2:58 pm

calculating rated power and bigger questions

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Michele Helou on Nov 30, 2012, 11:04 am

I cannot get the nameplate power from an Energy Star residential refrigerator used for a commercial project. I called the manufacturer, checked the manuals, etc. no luck. Can I calculate the...

Last reply: Danna Richey, Nov 8, 2018, 2:57 pm

More on UPS s

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Susan Di Giulio on Jan 31, 2015, 5:26 pm

Hi, I understand all the previous discussion UPSs but our situation is just a tad different,
The project in question is intensely tech related, and the UPS needed as backup is a 3 phase, 50...

Last reply: Danna Richey, Nov 8, 2018, 2:56 pm

No-break (UPS- UPS- Uninterruptible Power Supplies)

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Vitorio Lepiane on Jun 6, 2013, 10:19 am

I am trying to determine if we need to include " No-break (UPS - Uninterruptible Power Supplies) " in our Energy Star documentation for this credit.

Last reply: Danna Richey, Nov 8, 2018, 2:55 pm

UPS- Excluded or Included in Energy Star calculation

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Graeme Smith on Mar 2, 2014, 9:19 pm

I have two questions regarding the inclusion of UPS in the 'Energy Star' calculation for EAc1.4 in LEED v2009.

Q1. To Include UPS or not for Energy Star calculation?
I understand...

Last reply: Danna Richey, Nov 8, 2018, 2:55 pm

ENERGY STAR UPS- 160KW and 480V

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Carla Lopez on Nov 19, 2014, 4:34 pm

Hi,

It is of my best understanding that the UPSs are included as "eligible equipment" for both EAp2 and EAc1.4 as stated on the LEED for Commercial Interiors v2009 Reference Guide since...

Last reply: Danna Richey, Nov 8, 2018, 2:55 pm

green spec

CI-2009 EAc1.4: Optimize energy performance - equipment and appliances
posted by Lisa Logan on Aug 16, 2017, 3:37 pm

Are green spec products allowed in place of Energy Star? If you can prove they are equivalent in energy savings?

Last reply: Tristan Roberts, Aug 26, 2017, 4:16 pm