Energy Star Equipment- UPS SystemsCI-2009 EAp2: Minimum Energy Performanceposted by Rachel Manoguerra on Dec 19, 2018, 12:53 pm
I received a general review comment back on this credit regarding the inclusion of the UPS system in our Energy Star Equipment table. The project does not have point of use UPS, rather two... Last reply: Stacey Olson, Dec 20, 2018, 5:24 pm |
|
2007 versus 2010 ASHRAE formsCI-2009 EAp2: Minimum Energy Performanceposted by Denise Dauplaise on Feb 15, 2017, 4:30 pm
How have others filled in the ASHRAE Lighting Compliance Documentation form, specifically the "Space-by-Space Method" table? Since it was not expandable to add more than 7 spaces, we... Last reply: Marcus Sheffer, Nov 8, 2018, 2:18 pm |
|
Standby LossesCI-2009 EAp2: Minimum Energy Performanceposted by Ciaran McCabe on Jan 6, 2016, 7:44 am
How does one calculate the required Standby loss for a domestic hot water calorifier. I have the rated values in kwh/day from the manufacturer but not sure how or where I can get the required... Last reply: Marcus Sheffer, Jul 20, 2018, 1:00 pm |
|
CI Tenant SimulationCI-2009 EAp2: Minimum Energy Performanceposted by Charalampos Giannikopoulos on May 9, 2018, 11:10 am
Could anyone confirm that CI v3 projects registered after 04/08/2016 using the Alternative Compliance Path described in... Last reply: Charalampos Giannikopoulos, May 13, 2018, 12:29 pm |
|
EAP2- INPUT FileCI-2009 EAp2: Minimum Energy Performanceposted by SAMY Chamy on Jan 17, 2017, 4:34 am
Dear All:- Is there any specific input file available for LEED CI like "Revised input file 1.4" in LEED NC what are the documents we need to submit for EA CR 1.3 & EA PR 02 Last reply: Marcus Sheffer, May 9, 2018, 4:01 pm |
|
EAp2CI-2009 EAp2: Minimum Energy Performanceposted by Steve Zuwala on Dec 1, 2016, 3:40 pm
When listing non-energy star equipment we enter N/A in the Make or model column. This column is also used for Equivalent equipment as well, so the right had part of the form serves two purposes?... Last reply: Marcus Sheffer, Mar 7, 2018, 6:16 pm |
|
EAp2 Include Existing Equipment?CI-2009 EAp2: Minimum Energy Performanceposted by Lisa Granger on Sep 12, 2017, 5:03 pm
I didn't include computers, phones or printers in my documentation, because it was not purchased new for the project, but was reused from the previous location. I am confused by the response of... Last reply: Michael Smithing, Sep 13, 2017, 4:30 am |
|
ID+C v4- Existing Office Building: Lighitng & EnvelopeCI-2009 EAp2: Minimum Energy Performanceposted by Marc Maso on Apr 12, 2017, 10:00 am
We are doing a ID+C in a existing building, where the lighting and the envelope are the original ones. We doesn't modified this items. The original lighting (W/ft2) is better than the... Last reply: Marcus Sheffer, May 1, 2017, 10:04 am |
|
Basecase System ModelingCI-2009 EAp2: Minimum Energy Performanceposted by SAMY Chamy on Jan 17, 2017, 3:40 am
Dear All:- Greetings Currently we are working in LEED CI - office project The Building served with 5 no VRF and 2 no of Split A/c so we consider 7 no of systems so... Last reply: Marcus Sheffer, Jan 27, 2017, 9:48 am |
|
Brazilian equivalent standardCI-2009 EAp2: Minimum Energy Performanceposted by Aline Luther on Nov 22, 2016, 1:23 pm
I would like to know if there is any Brazilian Standard that can substitute the ANSI / ASHRAE / IESNA Standard 90.1-2007. According to the LEED 2009 for Commercial Interiors Rating System,... Last reply: Marcus Sheffer, Jan 17, 2017, 9:42 am |