Topic | Recent |
---|---|
Credit 3.2, Option 1, Path 2NC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Douglas Blakeslee on Mar 21, 2011, 4:35 pm
We are the... Last reply: David Hubka, Mar 23, 2011, 10:02 am |
|
Flushout of TI SpaceNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Carmen Cejudo on Jan 20, 2011, 1:28 pm
I have a building 27,000 sf Office building with a 2,000 sf TI space that will be rented out later. Because the TI space will be a shell, I'm wondering if it needs to be flushed out at the same... Last reply: Tristan Roberts, Jan 21, 2011, 10:47 am |
|
Multiple Units with Varying OSA RatesNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Patrick Farmer on Dec 28, 2010, 5:42 pm
Our project, as with most projects, has various air handling units with different OSA rates. To achieve the 14,000 cuft / sf, do we calculate the building as whole, or does each space have to... Last reply: Patrick Farmer, Dec 29, 2010, 12:50 pm |
|
Building flushout- option 2NC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Chellapillai Srinivasan on Oct 25, 2010, 1:26 am
How do on perform a building flush under option 2 for a 24 hr operating building. In LEED reference guide it is mentioned as "ventilation has to be started 3 hrs before the occupancy, and this... Last reply: Tristan Roberts, Oct 30, 2010, 8:28 am |
|
FCUs running during flush out- Y?NNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Chellapillai Srinivasan on Oct 12, 2010, 3:11 am
Is it required to run FCUs or any other If it is not required then we don’t want Last reply: Allison Beer McKenzie, Oct 12, 2010, 8:25 am |
|
Air Testing CriteriaNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Vivian Wan on Jul 22, 2010, 2:29 am
Is there any guideline to the sampling criteria such as the measurement interval during the normal occupied hours? In Hong Kong the sampling period required by Env. Dept is on 8-hour basis with... Last reply: Allison Beer McKenzie, Jul 22, 2010, 8:13 am |
|
Flush-out QuestionNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Leandro Silva on May 14, 2010, 8:34 am
We are completing a three-story story "vestiário" (shower and locker room) building in Rio de Janeiro, Brazil and have a question relative to EQc3.2. This building is naturally ventilated and to... Last reply: Tristan Roberts, May 16, 2010, 10:56 pm |
|
Air Quality TestingNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by April Ambrose on Apr 21, 2010, 5:29 pm
I'm having difficulty determining the best way to proceed in regards to utilizing the Air Quality Testing option to fulfill the requirements for this credit. This seems to be the most cost... Last reply: Shillpa Singh, May 3, 2010, 5:14 pm |
|
Flush Out During Occupancy for a 24/hr FacilityNC-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Alison Y Rivenburgh on Apr 7, 2010, 5:57 pm
Option 1, Path 2: "During each day of the flush-out period, ventilation must begin a minimum of 3 hours prior to occupancy and continue during occupancy." How does this fit into a building that... Last reply: Ben Stanley, Apr 8, 2010, 10:49 am |