Replacing filters prior to occupancy

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Ashley Love on Feb 15, 2017, 4:44 pm

**I did post this under the IEQc3.1 credit in Schools, too. My project is a school, but I wanted to make sure this question was seen, as my question is not "school only". I hope that is ok.**...

Last reply: Marcia Weekes, Feb 15, 2017, 5:05 pm

Pesticides during construction

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Omar Elrawy on Oct 4, 2016, 7:38 am

Dear all,
During the construction phase, the contractor asked to use pesticides once per week within the building. The reason is to offset rats and other insects that may harm the workers...

Last reply: Michelle Halle Stern, Oct 17, 2016, 10:02 am

One or Two Documents

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Omar Elrawy on Sep 19, 2016, 6:02 am

I'am confused about the document entitled "...

Last reply: Francis Chua, Sep 19, 2016, 8:04 am

Diesel Exhaust

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Lawrence Lile on Jul 24, 2016, 10:07 pm

We have a project where a heavy drill will be drilling micropiles in the basement. It is going to be a diesel powered drill, and it will make a heckuva lot of fumes. We plan to open all the...

Last reply: Michelle Halle Stern, Jul 25, 2016, 12:32 pm

Unrated filters

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by kathy zarsky on Dec 11, 2013, 2:59 pm

We are using Mitsubishi fan coil units on a project and provided a description of the permanent filter type in lieu of the...

Last reply: Lawrence Lile, Jul 24, 2016, 10:18 pm

IAQ management plan-during construction or before occupancy

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Kali Wolin on Jun 16, 2016, 1:43 pm

I am wondering if you can obtain the credit for Construction...

Last reply: Heather Holdridge, Jun 16, 2016, 8:42 pm

µg not µm?

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Takayuki Hirota on Jan 21, 2016, 11:37 pm

Reference guide Addenda allows to use filtration media with a minimum dust spot efficiency of 30% or higher and greater than 90% arrestance on a particle size of 3–10 "µg".

I suppose it is...

Last reply: Michelle Halle Stern, Jan 22, 2016, 9:45 am

Doing monthly photo report of IAQ management

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Indochine Engineering VN on Dec 13, 2015, 11:35 pm

Hi,

My project is under construction, but just structural work (finalizing substructure and launching superstructure). It is long way to furnishing and MEP work onsite. I have read several...

Last reply: Susan Walter, Dec 14, 2015, 6:25 pm

IAQ Management Plan and IAQ Management Specification Section

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Bridget Brock on Dec 10, 2015, 4:22 pm

I am working on a project where LEED was almost an after thought. I was brought into the project just after the 60% submittal. I am in a bit of a pinch with the 90% submittal due before...

Last reply: Saud Abdul Rasheed, Dec 13, 2015, 4:03 am

Air cleaning for IEQc3.1 Construction IAQ management plan

NC-2009 IEQc3.1: Construction IAQ management plan - during construction
posted by Marina Radchenko on Nov 4, 2015, 5:21 pm

We are going to apply for 1 point in credit IEQc3.1 but the Contractor is trying to avoid any ventilation during construction:
- no natural ventilation
- no ventilation by permanent...

Last reply: Tristan Roberts, Nov 27, 2015, 3:20 pm