CI-2009 MRc4:Recycled Contentposted by Patty Lloyd on
In LEED v3 CI are furniture and furnishings budget still required to be included in the MR credits 4,5, & 6?
No 2-year, 24 hour design storm data available
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Mario S. on
The 2 year, 24-hour design storm precipitation data is unavailable for the country. However, Historic rainfall data exists.
cold, dark warehouses in v4
posted by Michelle Rosenberger on
The majority of our Core & Shell warehouse projects are cold, dark shells with no tenants. We do not see a path for these projects to achieve certification at all in LEED v4 C&S.
BPDO calculator and Furniture
CI-v4 MRc4:Building product disclosure and optimization - sourcing of raw materialsposted by Michelle Rosenberger on
As I understand it, IDC projects are required to use Actual Materials cost and to include furniture in that cost.
Support Buildings impact on Heat Island Effect
NC-2009 SSc7.1:Heat Island Effect—Non-Roofposted by Daniela Mendez on
We have a project with a support building with no FTEs, hence, it is not a certifiable building according to the MPRs and we will only be using it to count the materials waste management.
Lagre building modeling suggestion
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, The project we are modeling is a huge one - a little more than 900 000 sq ft and it is not C&S.
College Campus, mixed use buildings, and public accessibility
NC-2009 SSc2:Development Density and Community Connectivityposted by Erica Downs on
We are attempting Op. 2: Community Connectivity on a college campus. We have plenty of services on campus that are open to the general public to meet the requirements.
Campus application
NC-v4 SSc4:Rainwater managementposted by Rob Hink on
Our LEED project site falls within a larger medical campus which has a campus-wide stormwater management plan which meets the credit requirements.
basecase System
NC-2009 EAp2:Minimum Energy Performanceposted by SAMY Chamy on
Dear Concern:- Greetings Our project is G+5 but A/c spaces are located in 3 Floors only and A/c area is totally below 10000 Square feet only (electrical heating only) so we have some queries in
Additional Flush-out Duration after Air Test Failed
Healthcare-v2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Kim Lombard on
If Option 2 for an air test fails, the remedy is .... "....conduct an additional flush-out with outside air and retest the noncompliant concentrations. Repeat until all requirements are met.