Log in
Forum » NC-2009 EAc5
Topic

Sub-metering Required?

NC-2009 EAc5: Measurement and Verification
posted by Dave Hubka on Nov 3, 2017, 5:17 pm

Hello,
We typically implement Option D of...

Last reply: Marcus Sheffer, Nov 6, 2017, 2:56 pm

EnergyStar Reporting

NC-2009 EAc5: Measurement and Verification
posted by Karl Heitman on Jul 31, 2017, 4:12 pm

comments for a page (http://www.leeduser.com/credit/NC-2009/EAc5?all-comments=true) and do a search. There are 41 instances of "Option 3" for this forum related to your question. For instance, see...

Last reply: Karl Heitman, Aug 1, 2017, 11:31 am

End Uses

NC-2009 EAc5: Measurement and Verification
posted by Matthew VanSweden on Nov 16, 2015, 9:58 am

I realize that EAc Advanced Energy Metering is not listed in the v4 credits that you are allowed to use on v2009 projects but has anyone had any success utilizing the v4 metering language of "...

Last reply: RETIRED, Jul 20, 2017, 10:43 am

AHU LEED Certificate

NC-2009 EAc5: Measurement and Verification
posted by Tota Yun on Jul 17, 2017, 6:37 am

to do with M&V so please post your questions in the appropriate LEED User Fourm. If you are asking about HVAC comliance issues then you should be posting in one of the EAp2 or EAc1 forums. Log...

Last reply: Marcus Sheffer, Jul 20, 2017, 10:17 am

EAc5 Option 3

NC-2009 EAc5: Measurement and Verification
posted by Jeff Wiedmeyer on May 16, 2017, 1:34 pm

I have a client who has chosen to meet MPR#6 by selecting Option 2: USGBC Approved Data Template. Is it possible to earn the 1 point under EAc5 option 3 without asking the client to change their...

Last reply: Jeff Wiedmeyer, May 16, 2017, 3:22 pm

Is water submetering required for LEED v3 2009?

NC-2009 EAc5: Measurement and Verification
posted by May Le on Apr 19, 2017, 12:56 pm

LEEDuser Expert 5903 thumbs up April 20, 2017- 11:48 am I was responding in the context of EAc5 since that is the forum the question was asked under. Yes for MPR #6 you provide energy and water data....

Last reply: Marcus Sheffer, Apr 20, 2017, 12:26 pm

ENERGY STAR Portfolio Manager

NC-2009 EAc5: Measurement and Verification
posted by Lou Niles II on Mar 30, 2017, 4:45 pm

When does the project have to register for the Energy Star Portfolio Manager? it is not clear if a registration number needs to be shown to comply for the Credit. The project is still...

Last reply: Lou Niles II, Mar 30, 2017, 7:58 pm

overall accuracy, anticipated areas of error susceptibility

NC-2009 EAc5: Measurement and Verification
posted by Leanne Niu on Mar 10, 2017, 3:09 am

There is a review comment in my project as follows:
It appears that the M&V plan provided does not specify the expected overall accuracy, anticipated areas of error susceptibility, and...

Last reply: Marcus Sheffer, Mar 14, 2017, 2:28 pm

Energy and Atmosphere credit #5

NC-2009 EAc5: Measurement and Verification
posted by James Goldfield on Feb 10, 2017, 1:43 pm

I had a question in regards to the energy and atmosphere credit #5 which states a need for a measurement and verification plan. My questions is does the contractor need to come up with this plan...

Last reply: Marcus Sheffer, Feb 10, 2017, 2:06 pm

GC Responsible for Implementing Option B?

NC-2009 EAc5: Measurement and Verification
posted by Marcia Weekes on Sep 22, 2014, 2:50 pm

Does anyone have any experience with projects where a...

Last reply: Matthew VanSweden, Sep 8, 2016, 11:29 am