Forum » NC-2009 EAc3
Topic

Exemplary Performance for EA Cr3 Enhanced Commissioning

NC-2009 EAc3: Enhanced Commissioning
posted by Deborah Lucking on Sep 24, 2010, 4:49 pm

The LEED BD+C Reference Manual (pg 301, item 9) mentions that "LEED for New Construction,......projects that conduct comprehensive envelope...

Last reply: Chris Ladner, Dec 14, 2010, 3:26 pm

Who can be the CxA?

NC-2009 EAc3: Enhanced Commissioning
posted by Keith Amann on Nov 9, 2010, 12:06 pm

We have a situation where an owner wants to directly hire a sub-division of the civil engineering firm of record to perform enhanced...

Last reply: Chris Ladner, Nov 23, 2010, 9:07 am

Commissioning of On-Site Renewable Energy Systems

NC-2009 EAc3: Enhanced Commissioning
posted by Lauren Sparandara on Oct 21, 2010, 4:03 pm

Today we received a clarification request for our Commissioning credit because our PV system has not yet been commissioned at the time of our submission. Our PV system has not yet been...

Last reply: Lauren Sparandara, Nov 10, 2010, 1:59 pm

Enhanced Commissioning and developing OPR & BOD

NC-2009 EAc3: Enhanced Commissioning
posted by Cynthia Estrada on Jul 27, 2010, 9:57 am

Thanks for the previous posts, great information. I have been investigating the responsibilities of this credit and to my understanding, LEED requires that the Owner develop the...

Last reply: Chris Ladner, Jul 27, 2010, 3:05 pm

STEP 7- Review contractor submittals

NC-2009 EAc3: Enhanced Commissioning
posted by Fabio Frescia on Jul 19, 2010, 4:57 am

Dear all partner,

Pls. can you clarify to me about the requirements of Review contractor submittals. Submittals here is included: material/ equipment AND Shop drawing? Or just material/...

Last reply: Chris Ladner, Jul 27, 2010, 2:54 pm

LEED only requires a Contract to be inplace for 10 Month Review

NC-2009 EAc3: Enhanced Commissioning
posted by Jean Marais on May 19, 2010, 4:14 am

The way I read this is that LEED only requires a contract to be in place for the 10 Month Review. The contract must include in its scope:

1) One 10 Month Review Plan which will incorporate...

CxA change during project?

NC-2009 EAc3: Enhanced Commissioning
posted by Margaret Montgomery on Mar 25, 2010, 6:52 pm

We've gotten the go to engage a...

Last reply: Chris Ladner, Mar 31, 2010, 11:18 pm

CxA

NC-2009 EAc3: Enhanced Commissioning
posted by Shriram Bhide on Mar 5, 2010, 12:57 pm

Thanks Kath,
This is a small building less than 50,000 SF.
USGBC allows one of the the team members to act as a...

You absolutely CAN use the

NC-2009 EAc3: Enhanced Commissioning
posted by Kath Williams on Mar 4, 2010, 4:33 pm

You absolutely CAN use the same person/firm for Fundamental and Enhanced...

Last reply: Kath Williams, Mar 5, 2010, 11:28 am

EA-3

NC-2009 EAc3: Enhanced Commissioning
posted by Shriram Bhide on Mar 2, 2010, 3:52 pm

We are doing a major renovation of a 49,200 gross sf building. According to the LEED 2009 reference guide, EA prerequisite #1, the...