Topic

HCFC count as CFC-based refrigerant?

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Chad Thurlow on Sep 27, 2017, 2:51 pm

Hello

The project I am working on has a pre-existing central plant. 3 of the refrigerants for it are HCFC R123. Do those count as CFC-based refrigerants? And if they do, how do I work...

Last reply: Trista Brown, Jul 6, 2018, 3:39 pm

refrigerant reccovery

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Faisal on Jul 29, 2017, 8:54 am

in EAp3 it says that there should be an EPA approved refrigerant recovery technician, is this requirement also for temporary units(like site offices site warehouse etc) or it is only for...

Last reply: Trista Brown, Aug 28, 2017, 5:44 pm

District Energy- 3rd Party Analysis Requirements

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Phil Stafa on Dec 6, 2016, 1:39 pm

Regarding EAp3 for a...

Last reply: Melissa Kelly, Jan 23, 2017, 10:48 am

R-438A

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Paula Hernandez on Jun 24, 2016, 11:45 pm

Hi,
We are working in a project that will have kitchen refrigerators, some of this equipment has refrigerant R-438A.
I believe that this refrigerant complies with the prerequisite,...

Last reply: Paula Hernandez, Jun 27, 2016, 3:18 pm

VRF system

NC-2009 EAp3: Fundamental Refrigerant Management
posted by GISELA FARHAT DE ARAUJO on Apr 5, 2016, 2:24 pm

We are using the vrf system on a project. Should i put as type of equipment Split AC or should i chose the "others" option?

Last reply: Melissa Kelly, Jun 27, 2016, 2:00 pm

If Purchasing Chilled Water from Campus Central Plant...

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Nelina Loiselle on Feb 3, 2015, 11:11 am

We have a project that we are modeling as purchased chilled water and steam because it is on a campus that includes a central plant. The campus sells the utilities to the department. For the...

Last reply: Melissa Kelly, Feb 18, 2015, 2:12 pm

How to document split system units

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Helene Lefkowitz on Jun 16, 2014, 7:47 pm

I am working on a hotel project that has multiple split system units. This means two part numbers, one for each unit, to account for all mechanical cooling equipment. In filling out the form for...

Last reply: Tristan Roberts, Jul 26, 2014, 1:42 am

Other equipment requiring refrigeration

NC-2009 EAp3: Fundamental Refrigerant Management
posted by R Jones on Apr 3, 2014, 5:56 am

Would we need to consider the refrigerants used for a split unit which is dedicated specifically for the cooling of a fume cupboard in a laboratory building?

Last reply: Tristan Roberts, Jul 26, 2014, 1:41 am

R407 F

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Charline SEYTIER on Dec 16, 2013, 11:23 am

Has anyone ever documented this prereq. with a system using R407F?
It's not part of the drop down list on the form and we're not sure it will comply.
Thanks in advance for your help...

Last reply: Charline SEYTIER, Dec 20, 2013, 3:49 pm

EAP3 online form limits to 10 systems?

NC-2009 EAp3: Fundamental Refrigerant Management
posted by Matt Scott on Nov 5, 2013, 4:29 pm

I am filling out my first EAP3 form and it won't allow me to add anymore systems beyond the first ten. I still have two more different models to add.

In general do you only input each...

Last reply: Charline SEYTIER, Dec 16, 2013, 11:38 am