Topic

SSp1 Required information

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by Victoria Rios Esteve on Jul 24, 2019, 3:01 pm

Hi everyone! 

I´m pretty new at LEED certification process, so I will really appreciate your help. 

We are close to upload the construction submittal on a project we have been...

Last reply: Allen Cornett, Oct 27, 2021, 2:22 pm

Compromise between Dust Control by Watering & Water Consumption

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by Abdulrahman Sherazy on Apr 9, 2012, 3:04 am

The best way I experienced in dust control measures in construction roads is to cover these roads by crushed stone, compact it by the compactor, and finally water it frequently. This reduces dust...

Last reply: Gordon Allen, Apr 20, 2021, 3:47 am

CONCRETE WASHOUT STATION-WATER REUSE

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by ISOLDA SALINAS on Feb 18, 2020, 6:50 pm

Hello Everyone,

We are working on a office building project located in an urban setting. Is it possible to re-use the water produced from the concrete washout station to mitigate dust in...

Ending ESC Monitoring- what stage in construction?

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by David Bell on May 28, 2019, 8:13 pm

Hi, I'm curious whether the USGBC/CaGBC has a generally accepted endpoint to...

Campus project- joint ESC plan and measures

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by Melinda Orova on Apr 14, 2016, 6:45 am

Hi,
We have a Campus project with 1 existing LEED certified building and 2 new buildings to be constructed on a Mastersite that is owned and operated by one company. The 2 new buildings...

Last reply: Summer Minchew, Jan 28, 2019, 8:38 am

Excavation material from LEED Project is moved outside the LEED boundary on adjacent land.

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by Adrian Arenas on Feb 24, 2018, 8:22 pm

Hello Everyone

In this particular project we have a condition that raised a question. We have large campus on a...

Last reply: Michael DeVuono, Mar 4, 2018, 9:02 am

LEED Boundaries & Construction Boundaries

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by soha yamani on Mar 8, 2015, 4:25 am

...

Last reply: Emily Purcell, Feb 12, 2018, 3:58 pm

No exposed soil- how to comply with ESC?

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by Michael E. Edmonds-Bauer on Nov 20, 2014, 1:12 pm

We have a small project that consists af an existing one level building that will have an major renovation. No exposed soil is present nor there is a garden or landscape therefor during the major...

Last reply: Ward Miller, Feb 12, 2018, 5:49 am

drainage area for sediment basin

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by Hongyun Zhou on Jun 9, 2016, 12:14 pm

when calculating the volume of sediment basin, what is the drainage area? Should I use footprint of the building or total land area of LEED boundary?

Last reply: Ward Miller, Feb 12, 2018, 5:06 am

Zero Lot Line

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by Omar Elrawy on Feb 25, 2016, 10:41 am

Dear all,
I have a project with an underground parking within the whole LEED project boundary, and landscape work above the underground parking, all around the above-grade...

Last reply: Ward Miller, Feb 8, 2018, 11:25 pm