Topic

FTE calculation for 24/7 facility

NC-2009 PIf3: Occupant and Usage Data
posted by Kyle Strock on Apr 20, 2020, 3:55 pm

We have a detention center intake facility which operates 24/7.  Monday thru Friday there are 16 employees per 8 hour shift.  On weekends there are 14 employees per 8 hour shift.  (We also have...

Last reply: Summer Minchew, Apr 20, 2020, 4:49 pm

Occupancy type- transient vs. resident

NC-2009 PIf3: Occupant and Usage Data
posted by Brooke Odom on Dec 6, 2012, 2:09 pm

We are working on a project for the Navy. It is a facility that acts as a hotel - navy personnel will stay at the facility for a few days until they head to their ship. We consider these...

Last reply: Susan Di Giulio, Oct 16, 2019, 1:09 pm

California ACP for LEED-NC v2009- is CALGreen checklist required?

NC-2009 PIf3: Occupant and Usage Data
posted by Susan Di Giulio on Feb 7, 2019, 6:43 pm

Hi,

Nearly all of our projects are in California. We have been using the CA ACP path for v2009 projects, which only applies to 6 pre-reqs and credits,  successfully since it came out. We...

FTE Computation Verification

NC-2009 PIf3: Occupant and Usage Data
posted by Summer on Nov 22, 2018, 2:37 am

My project is a theater and I was so confused how to compute the right...

Last reply: Summer, Dec 2, 2018, 9:03 pm

Complex Daily Occupancy- Daily Average Transients

NC-2009 PIf3: Occupant and Usage Data
posted by Joe Malone on Aug 21, 2018, 12:56 pm

We have a project with a complex occupancy. The facility is secure and staffed 24/7 by two groups, each group having 3 8-hour shifts. The majority (95%) of the workers spend about 1.5 hours in...

Last reply: David Eldridge, Aug 22, 2018, 5:14 pm

PIf3 Total number of residents

NC-2009 PIf3: Occupant and Usage Data
posted by Oscar Estevez on Apr 25, 2018, 9:46 pm

I have a Hospital project with one question on Table Plf3-3 Total number of residents:

NOTE: Assume two residents per one-bedroom unit, three residents per two-bedroom unit, etc., unless...

Last reply: David Eldridge, Aug 10, 2018, 4:02 pm

Reviewer Writes: Daily average FTE values should be higher than Peak FTE values

NC-2009 PIf3: Occupant and Usage Data
posted by Diego Prada on Jul 25, 2018, 5:25 pm

Greetings everyone,

We received a review for a Healthcare project. In it the review team is asking why "the Staff...

Last reply: David Eldridge, Aug 10, 2018, 3:51 pm

Theater and Retail Occupancy

NC-2009 PIf3: Occupant and Usage Data
posted by Summer on Aug 6, 2018, 2:25 am

Hello,

I have a Theater project that has a retail space operating 24/7 on the side of the building. I was wondering how to compute the occupancy of the retail since one of their transient...

Preschool Occupancy

NC-2009 PIf3: Occupant and Usage Data
posted by Heather Holdridge on Apr 12, 2018, 11:35 am

I received a preliminary design phase review comment on a preschool project for this PI form.  We entered identical values for the peak and average transient occupancy because the building is...

Last reply: David Posada, Apr 12, 2018, 6:16 pm

Occupants for Multi-purpose Hall and Canteen

NC-2009 PIf3: Occupant and Usage Data
posted by Sjansie Lachica on Apr 6, 2018, 1:45 am

My project is a mixed-use building which consist a whole floor assigned as multi-purpose hall and another floor as canteen. Do we need to determine the number of occupants in multi-purpose hall?...

Last reply: Summer Minchew, Apr 11, 2018, 8:49 am