Forum » Data-Centers-NC-v4.1 EAp2
Topic

Additional minimum requirement

Data-Centers-NC-v4.1 EAp2: Minimum Energy Performance
posted by Luis Andrade on Dec 9, 2024, 9:40 am

Hi everyone,

We're performing a LEED V4.1 Datacentre certification. LEED V4 stated that in addition to all "regular" minimum requirements, the project should also achieve "(...) a minimum...

Last reply: Marcus Sheffer, Dec 13, 2024, 8:41 am

solar PV Farm adjacent to Datacenter

Data-Centers-NC-v4.1 EAp2: Minimum Energy Performance
posted by S S on Jun 14, 2021, 1:56 am

Hello Everyone,

Greetings!

The proposed Datacenter building is intended to achieve LEED certification under LEED v4.1 BD+C Rating system - Datacenter

We are...

Last reply: Marcus Sheffer, Jun 14, 2021, 4:53 pm

Energy Model Points for LEED v4.1 Datacenter Building

Data-Centers-NC-v4.1 EAp2: Minimum Energy Performance
posted by S S on Jun 8, 2021, 9:04 am

Greetings to All,

Hope all are safe.

We are doing the energy model for office building in which electrical energy only used.

We know that, achieving the energy savings under...

Last reply: Marcus Sheffer, Jun 11, 2021, 3:17 pm