Basement renovation to a LEED Platinum Building

LEED Recertification: When and How
posted by  Faith Wilbert  on 

How do you go about a renovation in a LEED Plaitnum building? Do you have to do a recertification or another process. Theay are renovating 1 floor and I'm not sure the approach I need to take

1
Mon Apr 30, 2018, 11:23 pm

LEED V3 WEc1 V06 form Missing Resource?

NC-2009 WEc1:Water Efficient Landscaping
posted by  Melissa Merryweather  on 

We use 100% non-potable water in our project but the LEED v06 form still requires 50% reduction from baseline, but there is no calculator on the form and none separately available under Resources.

1
Fri Sep 15, 2017, 3:09 pm

underground infiltration structure LID?

CS-v4 SSc4:Rainwater management
posted by  Jens Apel  on 

I am not quite sure if the approach discussed in my project team is a viable way to achieve this credit and would like to check back with you.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Fri Sep 15, 2017, 10:50 am

Visitor parking only

CI-v4 LTc5:Reduced parking footprint
posted by  Karen Elliott  on 

We have an large office space in Central London that has 2 car parking spaces, but the staff will not be able to use them.  They will only be used in exceptional circumstances for visitors.

1
Fri Sep 15, 2017, 9:43 pm

electric bicycles can comply with Green vehicles

NC-v4 LTc8:Green vehicles
posted by  Hanh Truong  on 

Dear all,

My question is that whether electric bicycles can be considered as Green vehicles or not?

0

East-West Rout

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  Jalal Avades  on 

If our project is within a quarter mile of two bus stops. The two routes have the same route number but one goes East-West and the other is across the street and travels West-East.

6
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Thu Sep 14, 2017, 9:59 pm

Plaster and flat / non-flat and parking garage

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Marco Abdallah  on 

What is the reason for an distinction between non-flat (textured) and flat paints? Plaster has to be seen as coatings? What about underground parking lots, do they count as interior space (on the o

4
Construction Administrator/ LEED AP
Bywater Woodworks, Inc.
LEEDuser Basic Member
42 thumbs up
Thu Sep 14, 2017, 7:42 pm

Doctor Room

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Dinesh V  on 

What is the Category of Doctor Room as per ASHRAE 62.1.2007 Space classifications ? 

2
Thu Sep 14, 2017, 10:38 am

U value requirement for " Roof Hatch"

NC-2009 EAp2:Minimum Energy Performance
posted by   Faisal   on 

Hi...

    Does the proposed or basleine U or SHGC value requirement for the ROOF construction would also be applicable of " Roof Hatch"?

 

1
Thu Sep 14, 2017, 2:19 pm

Cx completion and LEED submissions

CI-v4 EAc1:Enhanced commissioning
posted by  Erin Rowe  on 

Two questions. 1) We are going for all commissioning points on a LEED V4 CI project.

0