Topic

Demonstrate Rice Husk to meet Green-e renewable Fuel Requirements

NC-v4.1 EAc5: Renewable energy
posted by Michael on Jul 15, 2024, 7:32 am

Hi LEED experts,

My project is a factory, using boilers with rice husk on-site. I received LEED review comments: if the Biomass is to be claimed as...

Last reply: Marcus Sheffer, Aug 8, 2024, 8:48 am

Tier 2-Renewable electricity and EACs

NC-v4.1 EAc5: Renewable energy
posted by Hashir Usman on Apr 6, 2022, 3:23 am

Hi everyone,

I'd like to ask if...

Last reply: Marcus Sheffer, Aug 4, 2024, 3:43 pm

Renewable Energy Calculator

NC-v4.1 EAc5: Renewable energy
posted by Mike Halcom on Jul 27, 2020, 12:18 pm

We are contemplating changeing form LEED v4 to LEED v4.1 for...

Last reply: Tyler Thumma, Jul 18, 2024, 9:16 am

LEED 4.1 Tier 2 & 3 Renewable Energy and District or Campus Thermal Energy (DES)

NC-v4.1 EAc5: Renewable energy
posted by Hans Marsman on Dec 2, 2023, 1:04 pm

We are working on a building connected to a campus central plant (...

Last reply: Gail Hampsmire, Apr 8, 2024, 9:21 am

Chinese Green Electricity Certificate "GECs"

NC-v4.1 EAc5: Renewable energy
posted by Josef Andersen on Jan 2, 2024, 4:39 am

Hi!

It came to my knowledge that USGBC does not accept Chinese Green Electricity Certificate "GECs". 

Allthough I have heard that projects have been usning GECs and earned...

Last reply: Marcus Sheffer, Jan 2, 2024, 2:55 pm

Ownership of Attributes: On-Site PV with Utility Program

NC-v4.1 EAc5: Renewable energy
posted by Summer Minchew on Dec 15, 2023, 9:26 am

The LEEDonline form for this credit requires us to, "Upload On-site Renewable Energy Systems...Contract and evidence of renewable attribute ownership.

  • For each on-site renewable...

Last reply: Marcus Sheffer, Dec 18, 2023, 10:00 am

v4.1 July 2023 Guide- EAC Arbitrage

NC-v4.1 EAc5: Renewable energy
posted by Christina Hohman on Sep 19, 2023, 12:13 pm

The newest v4.1 Guide (July 2023) has added the following language - "Note that while the previous versions of LEED allowed for EAC arbitrage for on-site systems, LEED v4.1 requires the owner to...

Last reply: Marcus Sheffer, Sep 22, 2023, 11:28 am

Offsite renewable energy production

NC-v4.1 EAc5: Renewable energy
posted by Subhashkumar A on Sep 19, 2023, 12:59 pm

The project is planning to achieve...

Last reply: Marcus Sheffer, Sep 19, 2023, 1:24 pm

v4.1 Renewable energy with v4.0 EAc2 Energy Performance

NC-v4.1 EAc5: Renewable energy
posted by Chris Flint Chatto on Aug 22, 2023, 1:24 pm

Just want to make sure its OK to use the v4.1 version of...

Last reply: Chris Flint Chatto, Aug 23, 2023, 2:16 pm

Waste Oil as renewable energy

NC-v4.1 EAc5: Renewable energy
posted by Vitor Leite Goncalves on Dec 22, 2022, 3:17 pm

Dear all,

One of our projects is a car dealership that is planning to re-utilize all waste oil generated onsite as space heating. Can this system be applied as...

Last reply: Marcus Sheffer, Dec 30, 2022, 10:47 am