The newest v4.1 Guide (July 2023) has added the following language - "Note that while the previous versions of LEED allowed for EAC arbitrage for on-site systems, LEED v4.1 requires the owner to...

Last reply: Marcus Sheffer, Sep 22, 2023, 11:28 am

Offsite renewable energy production

NC-v4.1 EAc5: Renewable energy
posted by Subhashkumar A on Sep 19, 2023, 12:59 pm

The project is planning to achieve...

Last reply: Marcus Sheffer, Sep 19, 2023, 1:24 pm

v4.1 Renewable energy with v4.0 EAc2 Energy Performance

NC-v4.1 EAc5: Renewable energy
posted by Chris Flint Chatto on Aug 22, 2023, 1:24 pm

Just want to make sure its OK to use the v4.1 version of...

Last reply: Chris Flint Chatto, Aug 23, 2023, 2:16 pm

Waste Oil as renewable energy

NC-v4.1 EAc5: Renewable energy
posted by Vitor Leite Goncalves on Dec 22, 2022, 3:17 pm

Dear all,

One of our projects is a car dealership that is planning to re-utilize all waste oil generated onsite as space heating. Can this system be applied as...

Last reply: Marcus Sheffer, Dec 30, 2022, 10:47 am

Tier 2-Renewable electricity and EACs

NC-v4.1 EAc5: Renewable energy
posted by Hashir Usman on Apr 6, 2022, 3:23 am

Hi everyone,

I'd like to ask if...

Last reply: Marcus Sheffer, Dec 30, 2022, 10:46 am

Renewable Energy Calculator

NC-v4.1 EAc5: Renewable energy
posted by Mike Halcom on Jul 27, 2020, 12:18 pm

We are contemplating changeing form LEED v4 to LEED v4.1 for...

Last reply: Misha Semënov-Leiva, Oct 17, 2022, 10:30 am

Tier 4 and Tier 5?

NC-v4.1 EAc5: Renewable energy
posted by Chris Flint Chatto on Jan 21, 2021, 1:31 pm

I see the credit description table lists tier 4 and tier 5...

Last reply: Paula Melton, Sep 14, 2022, 12:01 pm

Electric heat pumps- share of EE according to german law

NC-v4.1 EAc5: Renewable energy
posted by J Schütz on Aug 17, 2022, 5:58 am

Dear all,

for our projects in germany its quite controvers to communicate towards the project teams, why electric heat pumps cannot contribute to the credit renwable energy.

...

Last reply: Marcus Sheffer, Aug 17, 2022, 10:00 am

v4.1 Tier 1: Onsite Renewable PV Installation

NC-v4.1 EAc5: Renewable energy
posted by Stephanie Graham on May 3, 2021, 1:22 am

 The title of Table 1--"Points for Renewable Energy Procurement" is confusing, as it includes Tier 1.  As you indicated under another comment in this credit, it is possible to procure onsite...

Last reply: Stephanie Graham, Jul 25, 2022, 11:57 pm

LEED 4.1 NC Energy and Atmosphere

NC-v4.1 EAc5: Renewable energy
posted by Britt Valdez on Feb 21, 2020, 11:03 am

Hi, related to LEED 4.1 NC Energy and Atmosphere requirements: When purchasing Renewable Energy Credits (RECs) and/or carbon offsets, there is a one-year term option and a fifteen-year term...