Baseline Required Outdoor Airflow for Toilets
NC-v4 EAp2:Minimum energy performanceposted by Junaid Mujahid on
Hi Forum Users!
Contractor Declaration template
NC-v4 SSp1:Construction activity pollution preventionposted by Summer Gorder on
Does anyone have an example Declaration form tat complies with the documentation option below, if the GC can't locate photos:
Clarification on Baseline System Type and Exceptional Calculation for Phased Data Center Project
NC-v4 EAp2:Minimum energy performanceposted by Anurag Ghosh on
Dear Forum Members,
Where should Covered parking goes in exterior lighting format
NC-v4 EAp2:Minimum energy performanceposted by Rajat Wadhwa on
Hi,
I am working on a LEED project and I am confused as to Where should Covered parking goes in exterior lighting format.
Baseline HVAC Modelling - System 8, Electric Resistance Heating, and Heat Recovery (ASHRAE 90.1‑2010 Appendix G)
NC-v4 EAp2:Minimum energy performanceposted by Anurag Ghosh on
Hi All,
We are modelling a commercial tower under ASHRAE 90.1‑2010 Appendix G. The proposed design includes:
Regd. Primary Secondary Pump Arrangement in PRM Baseline System 8 Modelling
NC-v4 EAp2:Minimum energy performanceposted by Anurag Ghosh on
Hello All,
Feedback after pursuing PC132
Pilot-Credits MRpc132:Procurement of Low Carbon Construction Materialsposted by Dirk Kestner on
We are completing our pursuit of this Pilot Credit. Overall it went well. Here are a few comments and observations:
LEED BD+C v4.1 Transit
posted by Deepika Parmar on
We are currently working on a metro project comprising 13 stations (a mix of at-grade, elevated, and underground typologies) and 1 depot, spread across multiple locations within the city.
Is pc98 required to earn pc99?
Pilot-Credits IPpc99:Design for Enhanced Resilienceposted by Elizabeth Powers on
Can someone clarify if a project needs to have performed the hazard assessment in pilot credit 98 and during pre-design, in order to be eligible for this pilot credit, or does this pilot credit mea
Integrative Process for Health Promotion Pilot Credit (LEED)
posted by Michelle Amt on
Hi all,