posted by Dave Hubka on Sep 20, 2021, 2:48 pm

to a District cooling system I will update the forum with any lessons after the review Log in or register to post comments Torsten Biernat Baumann Consulting LEEDuser Basic Member 4 thumbs up December 13, 2021-...

Last reply: Triple Green Building Group, Apr 28, 2022, 9:55 am

Pilot-Credits WEpc94- No Cooling Tower

Pilot-Credits WEpc94: No Cooling Tower
posted by Adriana Hansen on Dec 8, 2021, 6:30 pm

We would like to know if there is an estimated date of closure.

We have many projects that don´t have cooling tower but attends the requirements of the pilot and have the baseline system...

Last reply: Irene García Sáez, Dec 23, 2021, 2:45 pm

No Cooling Tower pilot credit

Pilot-Credits WEpc94: No Cooling Tower
posted by Gail Napell on Oct 30, 2018, 12:59 am

Hi all

we're pursuing this credit and received a comment from the LEED reviewer that we need to submit the survey confirmation e-mail in order to achieve the credit.  The survey asks if we...

Last reply: Stephanie Graham, Dec 8, 2021, 11:17 pm

No Cooling Tower in LEED v2009 School

Pilot-Credits WEpc94: No Cooling Tower
posted by Sandra Schmid on Aug 31, 2021, 5:44 am

We are working on a LEED v2009 school project in Germany which is equipped with VRV refrigerating outdoor units for cooling of some rooms so there is no cooling tower, no use of latent heat of...

Has anyone earned this pilot credit on a core and shell building?

Pilot-Credits WEpc94: No Cooling Tower
posted by Jason Packer on Dec 10, 2019, 7:26 pm

We're working on a 15-storey core and shell mixed use office building in the Pacific North West. There is a 3-story podium level that has an allowed light manufacturing and other uses including...

Last reply: Daria Blanc-Mathieu, Feb 8, 2021, 3:29 am

No cooling tower- Group Approach Project

Pilot-Credits WEpc94: No Cooling Tower
posted by Alejandro Quiroga on Jan 3, 2021, 6:17 pm

Dear all,

I have also some doubts about this Pilot Credit (No Cooling Tower):

We are certifying a Business Park under LEED v4 O+M under Group Approach. The buildings don't have...

No cooling tower in design but core and shell spaces modeled as neutral with cooling tower in energy model.

Pilot-Credits WEpc94: No Cooling Tower
posted by Chris Yates on Sep 7, 2018, 9:48 am

A project I am working on meets all the requirements for the design (no cooling tower, no use of the latent heat of the evaporative cooling of water, no cooling from a District cooling system)....

Last reply: Maureen Drullard, Aug 25, 2020, 3:09 pm

Documenting WEpc94- No Cooling Tower

Pilot-Credits WEpc94: No Cooling Tower
posted by Noriko Nagazumi on Feb 5, 2019, 3:02 am

Maria Perzon PhD Bengt Dahlgren AB LEEDuser Basic Member October 10, 2019- 8:12 am Not an exact answer but i would refer you to this post linked below, hope that helps. https://leeduser.buildinggreen.com/forum/pilot-credit-no-cooling-tower-v4-bcd Log in or register to post comments Bipin Karki Sustainability Project Manager LEEDuser Premium Member 87 thumbs up October 11, 2019- 10:59 am Hello Noriko,  You can apply for the No Cooling Tower pilot alternative compliance path. You need to include the following as part of the submittals: a. A copy of the Pilot Credit registration confirmation email b. A copy of the Pilot Credit survey...

Last reply: Bipin Karki, Oct 11, 2019, 10:59 am

No cooling tower Sweden

Pilot-Credits WEpc94: No Cooling Tower
posted by Sandra Holmström on Feb 15, 2019, 12:34 pm

We are pursuing this pilot credit as ACP for a Swedish Project. We Think it is fair that Projects without cooling Towers can achieve the no cooling Tower credit too, since you do not use any...

Last reply: Maret Heidelberg, Jun 21, 2019, 5:12 am

LEED EB-OM- Office Building- Portugal- No Cooling Tower

Pilot-Credits WEpc94: No Cooling Tower
posted by Goreti Guedes on Feb 12, 2019, 12:26 pm

Dear all,

I have also some doubts about this Pilot Credit (No Cooling Tower):

Requirement:

''the baseline system designated for the building using ASHRAE 90.1-2010...