Forum quick links
How to model process chilled water load?
NC-v4 EAp2:Minimum energy performanceposted by Eric Dixon on
My proposed design for lab utilizes a heat recovery chiller connected to geo-exchange. There is a 40 ton process chilled water load on the heat recovery chiller.
LTc7 - Reduce parking footprint - examplary performamce
NC-v4 LTc7:Reduced parking footprintposted by Maria Peralta on
Hello!
Maximum Distance from Parking to Site
NC-v4 LTc7:Reduced parking footprintposted by Laraib Raza on
Hello All LEED Users,My question is what is the maximum distance allowed from the building(site) to parking? If the Parking is located outside of the site boundary?
*time sensitive* Presidential election advocacy opportunity
posted by Clark Brockman on
Greetings to all of the sustainability leaders in the Green Commons!
Option 1 No Parking or Reduce Parking
NC-v4.1 LTc7:Reduced Parking Footprintposted by Bryna Dunn on
When I am looking at the credit language, the first two requirement statements not connected by "OR" or "AND". The third statement says "Alternatively". Has anyone submitted successfull
Heat recovery HVAC
NC-v4.1 EAp2:Minimum Energy Performanceposted by Josef Andersen on
Hi!
We are currently discussing a design solutions for the HVAC in a project that should fulfill LEED requirements.
High Voltage Equipment testing scope
CS-v4.1 EAp1:Fundamental Commissioning and Verificationposted by Daisuke Miura on
Hi, I am working on a LEED project as Commissioning Agent.
This is a commercial building project that is build from green field in Japan.
Waste handling of process installation
NC-v4.1 MRp2:Construction and Demolition Waste Managementposted by Josef Andersen on
Hi!
We are constructing industry buildings for car manufactoring. The project phase are divided between our FM team and the process team.
Lighting Boundary Modification - Light Trespass: Option 1. BUG Rating Method Only?
NC-v4 SSc6:Light pollution reductionposted by Lenka Matějíčková on
The LEED manual states that, under certain conditions, the lighting boundary can be modified (e.g.when the property line is adjacent to a public street, alley, or transit corridor, the lighting bou