Topic | Recent |
---|---|
Distinct Structures- Pump HouseSchools-NC-v4 MPR2: Must use reasonable LEED boundariesposted by Kathryn Haeberle on Sep 10, 2021, 5:59 pm
We are building a replacement elementary school on an existing school site. The school will get water from new wells we are installing that require a separate 'pump house'. This pump house will... |
|
Two additions to school but not connected, should we exclude one...Schools-NC-v4 MPR2: Must use reasonable LEED boundariesposted by Alara Brinton on May 12, 2021, 11:16 am
I do not have a coach assigned to this project, however I have a question regarding the LEED boundary and MPR interpretation for an addition project. I have emailed... Last reply: Alara Brinton, May 13, 2021, 9:48 am |
|
Multiple School Additions and Determining LEED BoundarySchools-NC-v4 MPR2: Must use reasonable LEED boundariesposted by Stephen Sgro on Mar 19, 2018, 1:59 pm
We are currently working on a school project that includes four additions to be constructed over several phases. The school would like to seek LEED certification for one of the... Last reply: Stephen Sgro, Mar 26, 2018, 5:29 pm |
|
New building and renovated building within same certificateSchools-NC-v4 MPR2: Must use reasonable LEED boundariesposted by Ricardo Sá on Feb 1, 2017, 6:00 am
I am currently involved in a project for a K-12 school which is comprised of a new building (classrooms, teacher rooms, common areas, auditorium, library, bar and parking) and an existing... Last reply: Tristan Roberts, Aug 26, 2017, 12:16 pm |
|
LEED Schools or LEED CI?Schools-NC-v4 MPR2: Must use reasonable LEED boundariesposted by Peter Doo on Jul 31, 2017, 10:58 am
We are pursuing an interior renovation of a k-12 school building to ongoing school use. Can we use LEED CI or must we use LEED Schools? Last reply: Tristan Roberts, Aug 26, 2017, 12:13 pm |
|
Addition Project Boundary remote from existing parkingSchools-NC-v4 MPR2: Must use reasonable LEED boundariesposted by Larry Turbes on Mar 6, 2014, 4:30 pm
We are planning on certifying a school addition. The existing building is not certified and there will be a clear boundary between the addition and existing building. The addition will have a... Last reply: Tristan Roberts, Mar 6, 2014, 4:46 pm |