feedbackPilot-Credits EApc65: Monitoring based commissioningposted by emily reese moody on Dec 15, 2015, 7:59 pm
There was some confusion at the on start of the process as to who owned the analyzing and reporting of the data. The confusion seemed to be due to the overlap of the tasks for this credit and the... |
|
when we register a pilot credit....Pilot-Credits EApc65: Monitoring based commissioningposted by Gail Napell on Nov 14, 2015, 3:03 pm
we registered the pilot credit; is it supposed to show up in the project in LEEDonline? how do we upload the documentation???? thanks for guidance - |
|
Monitoring PeriodPilot-Credits EApc65: Monitoring based commissioningposted by Mari Hamasaki on Feb 4, 2015, 1:36 pm
What is the required monitoring period for this credit? |
|
more informationPilot-Credits EApc65: Monitoring based commissioningposted by Gail Napell on Dec 7, 2014, 5:21 pm
Hi all - Last reply: David Eldridge, Dec 7, 2014, 5:50 pm |