How many sample locations for measurement?CI-v4 EQc9: Acoustic performanceposted by Brian Salazar on Dec 31, 2018, 10:19 am
I am looking to take mic measurements of the ambient noise in our space to provide a baseline for HVAC Background Noise. The Acoustic performance Calculator specifies the following: ... Last reply: Aparna Pradeep Kumar, Aug 24, 2022, 11:29 am |
|
Use of alternative standards- UKCI-v4 EQc9: Acoustic performanceposted by R Jones on May 31, 2022, 6:54 am
Hi - what other standards are allowed as an equivalent to the ASHRAE standard? is the British Council for Offices (BCO) guidance accepted for all parts ? thanks |
|
adjacent spaces outside scope of work?CI-v4 EQc9: Acoustic performanceposted by Erin Holdenried on Nov 17, 2021, 9:42 am
For LEED projects that consist of tenant space within a larger building, do they have to consider adjacencies to spaces outside the scope of work? Last reply: Adam Paul, Feb 3, 2022, 5:24 pm |
|
Is it ok to have furniture installed when measuring T60 (reverberation)?CI-v4 EQc9: Acoustic performanceposted by BEE Incorporations on Oct 29, 2020, 10:46 pm
I suspect it's ok but I just want to be sure because it's not indicated in the LEED Guide. Thank you. |
|
Bar SpaceCI-v4 EQc9: Acoustic performanceposted by Kevin Gilleran on Mar 22, 2018, 5:08 pm
Hi. We are working on a TI within a shell building which will have a bar, seating, lounge area, kitchen prep areas with support spaces and its own restrooms. No office function etc. I dont see... Last reply: Kevin Gilleran, Aug 24, 2018, 1:59 pm |
|
Office, conference room to Hallway, stairs STCc InterpretationCI-v4 EQc9: Acoustic performanceposted by Jeffrey Fullerton on Jan 30, 2018, 3:37 pmKen Shook Partner Longman Lindsey LEEDuser Expert 5 thumbs up August 8, 2018- 9:52 am There was a previous question pertaining to this topic, linked below: https://leeduser.buildinggreen.com/forum/conference-room-vs-meeting-room-sliding-doors Log in or register to post comments ... Last reply: Ken Shook, Aug 8, 2018, 9:52 am |
|
TI scope vs. CS base buildingCI-v4 EQc9: Acoustic performanceposted by Michelle Rosenberger on Apr 25, 2017, 4:24 pm
How do we achieve this credit based only on TI scope of work? If the core & shell building does not pursue acoustic performance compliance, how do we deal with core restroom or mechanical... Last reply: Tristan Roberts, Aug 26, 2017, 2:52 pm |
|
Copy area in office- acoustical treatmentCI-v4 EQc9: Acoustic performanceposted by Leticia SooHoo on Jul 11, 2016, 2:29 pm
Hi, we are designing an office space which will have a copy area ( 2 to 3 floor model copiers) adjacent to an open office space. The copy area will have full height walls enclosing the area but... Last reply: Daniel Hicks, Jan 19, 2017, 4:22 pm |