5 year replacement period?CI-v4 EAp3: Fundamental Refrigerant Managementposted by Laura Charlier on Sep 17, 2024, 2:03 pm
"For existing buildings with existing equipment or projects that use existing central plants, teams will need to check if CFC-based refrigerants are being used. If they are, LEED requires either... |
|
Fundamental refrigerant management for a "District Energy System"CI-v4 EAp3: Fundamental Refrigerant Managementposted by Ralph Bicknese on Jan 18, 2018, 12:12 pm
To be clear, does the upstream equipment in a District Energy System need to be considered for the prerequisite or only for the enhanced refrigerant management credit? Based on the "project type... |
|
Cooling TowersCI-v4 EAp3: Fundamental Refrigerant Managementposted by Laura Charlier on Nov 2, 2017, 1:48 pm
If cooling tower is being replaced as part of project, does that need to be included in calcs? |
|
Existing Chillers in Basement (not in project boundary)CI-v4 EAp3: Fundamental Refrigerant Managementposted by Heather Zeto on Aug 18, 2017, 11:14 am
Our project is a 4-floor fit-out of a hospital tower (Less than 200,000 SF of an existing 8 Million SF building). There are (2) large chillers in the basement (not part of our project scope)... Last reply: Ashwini Arun, Aug 28, 2017, 6:14 pm |
|
Existing small HVAC&R unitsCI-v4 EAp3: Fundamental Refrigerant Managementposted by Mercedes Ferreira on Apr 7, 2017, 7:56 pm
For the Fundamental Refrigerant Management credit under the ID+C rating system, when the requirement says, "Existing small HVAC&R units (defined as containing less than 0.5 pound (225 grams)... Last reply: Ashwini Arun, Aug 28, 2017, 5:31 pm |