DES Cooling tower

EBOM-v4 WEc3: Cooling tower water use
posted by Elyse Dufrene on Sep 11, 2018, 7:44 am

Can...

Last reply: Elyse Dufrene, Mar 15, 2019, 11:21 am

Project Currently Running at 10 Cyc- Am I eligible for 3 pts

EBOM-v4 WEc3: Cooling tower water use
posted by Robert Cox on Jul 3, 2017, 4:44 am

Hello - Based on the water analysis provided by our vendor, we can achieve 11 cycles prior to requiring treatment. We are currently using 10 cycles. Does this qualify for 2 or 3 points? The...

Last reply: Trista Little, Aug 21, 2017, 9:09 pm

100% well or non-potable water

EBOM-v4 WEc3: Cooling tower water use
posted by Elizabeth Dunn on Nov 14, 2016, 12:29 am

Our building uses 100% well or non-potable water. We are pulling the water analysis but even if we aren't meeting the fullest number of cycles, we aren't using any water from the municipal...

Last reply: Craig Sheehy, Nov 17, 2016, 6:56 pm

100% well or non-potable water

EBOM-v4 WEc3: Cooling tower water use
posted by Elizabeth Dunn on Nov 14, 2016, 12:29 am

Our building uses 100% well or non-potable water. We are pulling the water analysis but even if we aren't meeting the fullest number of cycles, we aren't using any water from the municipal source...

Number of cycles

EBOM-v4 WEc3: Cooling tower water use
posted by Jonathan Miller on Feb 18, 2014, 11:03 pm

What is the number of cycles necessary to achieve 1 point? 10?

Last reply: Batya Metalitz, Feb 19, 2014, 10:51 am

Number of cycles

EBOM-v4 WEc3: Cooling tower water use
posted by Jonathan Miller on Feb 18, 2014, 11:03 pm

What is the number of cycles necessary to achieve 1 point? 10?