Forum quick links
cold, dark warehouses in v4
posted by Michelle Rosenberger on
The majority of our Core & Shell warehouse projects are cold, dark shells with no tenants. We do not see a path for these projects to achieve certification at all in LEED v4 C&S.
BPDO calculator and Furniture
CI-v4 MRc4:Building product disclosure and optimization - sourcing of raw materialsposted by Michelle Rosenberger on
As I understand it, IDC projects are required to use Actual Materials cost and to include furniture in that cost.
Support Buildings impact on Heat Island Effect
NC-2009 SSc7.1:Heat Island Effect—Non-Roofposted by Daniela Mendez on
We have a project with a support building with no FTEs, hence, it is not a certifiable building according to the MPRs and we will only be using it to count the materials waste management.
Lagre building modeling suggestion
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, The project we are modeling is a huge one - a little more than 900 000 sq ft and it is not C&S.
College Campus, mixed use buildings, and public accessibility
NC-2009 SSc2:Development Density and Community Connectivityposted by Erica Downs on
We are attempting Op. 2: Community Connectivity on a college campus. We have plenty of services on campus that are open to the general public to meet the requirements.
Campus application
NC-v4 SSc4:Rainwater managementposted by Rob Hink on
Our LEED project site falls within a larger medical campus which has a campus-wide stormwater management plan which meets the credit requirements.
basecase System
NC-2009 EAp2:Minimum Energy Performanceposted by SAMY Chamy on
Dear Concern:- Greetings Our project is G+5 but A/c spaces are located in 3 Floors only and A/c area is totally below 10000 Square feet only (electrical heating only) so we have some queries in
Additional Flush-out Duration after Air Test Failed
Healthcare-v2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Kim Lombard on
If Option 2 for an air test fails, the remedy is .... "....conduct an additional flush-out with outside air and retest the noncompliant concentrations. Repeat until all requirements are met.
Average ADC%
NC-v4 MRc5:Construction and demolition waste managementposted by Michelle Rosenberger on
The tracking form is now asking for average ADC produced by the sorting facility. This isn't part of the reporting we get from them. Is this optional?
Services on campus
NC-2009 SSc2:Development Density and Community Connectivityposted by Lauren Sparandara on
We recently received a review comment that said that we could not count the services located on our university campus and freely available to all of our project's FTE.