Advanced Gas Meter and SubmeterNC-v4 EAc3: Advanced Energy Meteringposted by Edgar Arevalo on Aug 16, 2022, 10:05 am
It's been pretty easy to find advanced electrical submeters that meet all the characteristics from LEED, but it's been such as challenge to find one for natura gas intake. Has anyone found... Last reply: Marcus Sheffer, Aug 16, 2022, 12:32 pm |
|
Advanced Metering- Gas metersNC-v4 EAc3: Advanced Energy Meteringposted by Pournamasi Rath on Apr 15, 2021, 3:00 pm
Hi, The Mechnical team on our project is providing separate gas meters as reuqired by the credit, but they specified that the meters are supplied by the utility provider (Nation Grid in... Last reply: Marcus Sheffer, Aug 16, 2022, 12:31 pm |
|
NCv4- EAc Advanced Metering- VRF systemNC-v4 EAc3: Advanced Energy Meteringposted by Margaret Montgomery on Mar 5, 2018, 3:29 pm
We have a clinic project that is all electric, and will be submetering to meet the Advanced Metering criteria, but we're not finding clarity on one particular point. We will be submetering... Last reply: Marcus Sheffer, Jul 18, 2022, 2:30 pm |
|
Hotel Rooms Advanced Metering ClarificationNC-v4 EAc3: Advanced Energy Meteringposted by Francesco Lupoi on Jun 14, 2022, 4:40 am
Hi everyone! In a hotel project we have to meter every single consumption ( lighting, power outlets, HVAC SYSTEM) for every room switchboard panels or we could metering the rooms... Last reply: Marcus Sheffer, Jun 24, 2022, 3:03 pm |
|
All meters in the system must be capable of reporting hourly, daily, monthly, and annual energy use.NC-v4 EAc3: Advanced Energy Meteringposted by Chad Thurlow on Apr 19, 2022, 2:47 pm
To Whom This May Concern One of the meter requirement states "All meters in the system must be capable of reporting hourly, daily, monthly, and annual energy use." My question is, does it... Last reply: Marcus Sheffer, Apr 22, 2022, 8:50 am |
|
where and how to install advanced meters?NC-v4 EAc3: Advanced Energy Meteringposted by Sara BENLOUBA on Dec 15, 2021, 11:02 am
Dear all, We have a tower with multi-storey building, made up of 3 components: Offices, hotel and residential. We follow as a reference the " BD+C NC " The... Last reply: Sara BENLOUBA, Dec 23, 2021, 5:07 am |
|
Whole Building MetersNC-v4 EAc3: Advanced Energy Meteringposted by Dave Hubka on Apr 15, 2021, 2:12 pm
I think whole building meters must also meet the Advanced Metering requirements per the Requirements section of the reference guide however the rest of the reference guide, credit template, and... Last reply: Marcus Sheffer, Dec 10, 2021, 9:37 am |
|
Definition "individual energy end use"?NC-v4 EAc3: Advanced Energy Meteringposted by Lise Dannesboe on Jan 6, 2017, 5:58 am
Hi, i went though all the comments on this forum and cannot really find a clear answer to the question i have when i read the sentence: "any individual energy end uses that represent 10% or more... Last reply: Marcus Sheffer, Mar 4, 2021, 9:38 am |
|
Fans as an End UseNC-v4 EAc3: Advanced Energy Meteringposted by Pooja Sannamani on Jan 6, 2021, 7:01 pm
Hi, we'd like to make sure we are meeting the intent of the credit correctly when it comes to fans. We use IES for energy models which typically breaks fans into meters for exhaust fans... Last reply: Pooja Sannamani, Jan 8, 2021, 5:16 pm |
|
Tenancy areas with low relevanceNC-v4 EAc3: Advanced Energy Meteringposted by Ricardo Sá on Sep 22, 2020, 1:08 pm
Dear All Last reply: Marcus Sheffer, Nov 13, 2020, 10:16 am |