CxA Experience Validation

CS-v4 EAc1: Enhanced Commissioning
posted by Michaël Briffaz on Oct 19, 2022, 9:21 am

Hey,

We would like to submit the experience and references for a...

Defining Minimum Scope of Work of MBCx to Optimize the Investment Cost for The Building Owner

CS-v4 EAc1: Enhanced Commissioning
posted by Titinant on Oct 1, 2020, 5:29 am

Referring to LEED V4 EAc1 guideline, MBCx is the integration of 3 components: (1) Permanent energy monitoring systems, (2) Real-time energy analysis, (3) Ongoing...

Last reply: Scott Bowman, Apr 26, 2021, 12:25 pm

CxA Role- Limited central plant installed

CS-v4 EAc1: Enhanced Commissioning
posted by Ciaran McCabe on Nov 5, 2019, 1:15 pm

Hi,

We are working on a LEED project where the client is considering installing minimal central HVAC plant as part of the core and shell works. Therefore the role of the...

Last reply: Scott Bowman, Feb 28, 2020, 4:10 pm

Monitoring-based Cx for CS projects

CS-v4 EAc1: Enhanced Commissioning
posted by Shannon Oletic on Mar 14, 2019, 3:31 pm

What are the required measurement points for a core and shell project?

Our project is a small core and shell building designed for retail, with limited M+E equipment (ERVs, RTUs, lighting...

Last reply: Dave Hubka, Aug 13, 2019, 1:09 pm

CS EA credit Enhanced Cx- who can serve as CxA

CS-v4 EAc1: Enhanced Commissioning
posted by Deeta Bernstein on Jul 22, 2019, 2:08 pm

Any precedent in pursuing the Enhanced...

Last reply: Scott Bowman, Aug 11, 2019, 5:30 pm

Scope of Envelope Commissioning

CS-v4 EAc1: Enhanced Commissioning
posted by Michelle Rosenberger on Apr 25, 2018, 1:50 pm

We have a core and shell warehouse project that has no tenant buildout, i.e., no conditioned space, and therefore no thermal envelope. We interpret the vague requirements for envelope...

Last reply: Elizabeth Cassin, Apr 30, 2018, 11:17 pm

Envelope Commissioning

CS-v4 EAc1: Enhanced Commissioning
posted by Agnieszka Rylska on Sep 25, 2017, 12:49 pm

Hi,

I have a question about Envelope Commissioning. For commercial building what tests are nessesery ? Air leakge testing is enough ? Or should I also test the building with thermal...

Building Envelope Seasonal Testing & General Comment

CS-v4 EAc1: Enhanced Commissioning
posted by Brian Salazar on Aug 3, 2017, 2:37 pm

Hi! In general, the guidelines for this credit are...very general and vague. For example "Verify Seasonal Testing" -- Are there specific guidelines or requirements under Seasonal Testing that...

Last reply: Dave Hubka, Aug 15, 2017, 8:46 pm

Documentation upload to LEED Online

CS-v4 EAc1: Enhanced Commissioning
posted by Erin Rowe on Jul 7, 2017, 2:51 am

We are just getting ready to submit LEED CI V4...

Last reply: Dave Hubka, Aug 15, 2017, 8:28 pm

Different CxA for Construction other than one hired duringDesign

CS-v4 EAc1: Enhanced Commissioning
posted by mohammad Hassan on Jun 1, 2017, 4:50 am

Can a different...

Last reply: Dave Hubka, Aug 15, 2017, 8:18 pm