Topic

Baseline Design Supply Airflow Rate Temperature Difference 90.1-10 para. G3.1.2.9.1

NC-v4 EAp2: Minimum Energy Performance
posted by Michael Callan on Mar 30, 2022, 1:27 pm

Hello,

I have a qeustion regarding ASHRAE 90.1-10, paragraph G3.1.2.9.1 which states that for baseline systems 1through 8, design supply airflow rates for the baseline building shall be...

Last reply: Tyler Thumma, Apr 12, 2022, 9:47 am

ASHRAE Standard 90.1- 2016 in LEED v4

NC-v4 EAp2: Minimum Energy Performance
posted by Greenlab on Mar 28, 2022, 12:55 pm

Dear all,

While following LEED v4 EA Minimum Energy Performance, can we use ASHRAE Standard 90.1 - 2016, as it's more stringent than the 2010 version, instead of ASHRAE Standard 90.1 -...

Last reply: Jamy Bacchus, Mar 28, 2022, 2:36 pm

Baseline Case Outdoor Air Modeling

NC-v4 EAp2: Minimum Energy Performance
posted by Mankisha Veng Veng on Mar 17, 2022, 2:58 am

Dear Concern:-

Our Design project does not have DCV (Demand Control Ventilation ) so can we model the fresh air identically Baseline and prposed case as per ASHRAE 90.1.2010 ...

Last reply: Cory Duggin, Mar 21, 2022, 12:17 pm

District heating and Cooling

NC-v4 EAp2: Minimum Energy Performance
posted by Greenlab on Jun 21, 2018, 2:36 pm

Hello Everyone,

I am currently modeling (Design Builder) a building which essentially consists of a mix of laboratories and office spaces. This building is supplied by a District heating (...

Last reply: Tyler Thumma, Feb 17, 2022, 10:22 am

Autopsy Spaces

NC-v4 EAp2: Minimum Energy Performance
posted by Cory Duggin on Jan 17, 2022, 3:02 pm

Would autopsy and associated support spaces be considered a lab space to be included on systems under G3.1.1 exception c requiring turn down at night?  I ask because these same spaces in a...

Last reply: Tyler Thumma, Feb 17, 2022, 10:12 am

Purchased Condenser Water

NC-v4 EAp2: Minimum Energy Performance
posted by Saif Alsaeed on Jan 7, 2022, 11:50 am

Hello,

I am working on a project that has 2 buildings each one will be submitted to LEED as a separate project. The first building is an office building that is served by water cooled self...

Last reply: Tyler Thumma, Jan 14, 2022, 11:07 am

Automatic Receptacle Controls- IECC 2018 v ASHRAE 90.1-2010

NC-v4 EAp2: Minimum Energy Performance
posted by Cindy Quinn on Jun 4, 2020, 6:08 pm

We are working on a project that has to comply with IECC 2018 in order to meet the city’s energy...

Last reply: Jamy Bacchus, Jan 5, 2022, 5:46 pm

Possibility of unconditioned regularly occupied space

NC-v4 EAp2: Minimum Energy Performance
posted by Alessandro Zuanon on Dec 16, 2021, 6:46 am

Hello,

i'm in the case of a regularly occupied space (a mechanical workshop in a warehouse), in which there is the possibility of no heating or cooling system installation. Is it possible...

Last reply: Afogreen Build, Dec 21, 2021, 6:01 pm

Baseline Lab Systems

NC-v4 EAp2: Minimum Energy Performance
posted by Cory Duggin on Dec 15, 2021, 12:22 pm

I got a comment on a project that said G3.1.1 exception c means that all qualifying lab spaces would be assigned to one system 5/7 for the whole building not one per floor.  Is that correct?

Last reply: Tyler Thumma, Dec 20, 2021, 8:28 am

Fine or bulky material

NC-v4 EAp2: Minimum Energy Performance
posted by Francesco Passerini on Jun 10, 2021, 9:10 am

In order to specify the lighting power...

Last reply: Dave Hubka, Dec 17, 2021, 3:50 pm