Baseline Design Supply Airflow Rate Temperature Difference 90.1-10 para. G3.1.2.9.1NC-v4 EAp2: Minimum Energy Performanceposted by Michael Callan on Mar 30, 2022, 1:27 pm
Hello, I have a qeustion regarding ASHRAE 90.1-10, paragraph G3.1.2.9.1 which states that for baseline systems 1through 8, design supply airflow rates for the baseline building shall be... Last reply: Tyler Thumma, Apr 12, 2022, 9:47 am |
|
ASHRAE Standard 90.1- 2016 in LEED v4NC-v4 EAp2: Minimum Energy Performanceposted by Greenlab on Mar 28, 2022, 12:55 pm
Dear all, While following LEED v4 EA Minimum Energy Performance, can we use ASHRAE Standard 90.1 - 2016, as it's more stringent than the 2010 version, instead of ASHRAE Standard 90.1 -... Last reply: Jamy Bacchus, Mar 28, 2022, 2:36 pm |
|
Baseline Case Outdoor Air ModelingNC-v4 EAp2: Minimum Energy Performanceposted by Mankisha Veng Veng on Mar 17, 2022, 2:58 am
Dear Concern:- Our Design project does not have DCV (Demand Control Ventilation ) so can we model the fresh air identically Baseline and prposed case as per ASHRAE 90.1.2010 ... Last reply: Cory Duggin, Mar 21, 2022, 12:17 pm |
|
District heating and CoolingNC-v4 EAp2: Minimum Energy Performanceposted by Greenlab on Jun 21, 2018, 2:36 pm
Hello Everyone, I am currently modeling (Design Builder) a building which essentially consists of a mix of laboratories and office spaces. This building is supplied by a District heating (... Last reply: Tyler Thumma, Feb 17, 2022, 10:22 am |
|
Autopsy SpacesNC-v4 EAp2: Minimum Energy Performanceposted by Cory Duggin on Jan 17, 2022, 3:02 pm
Would autopsy and associated support spaces be considered a lab space to be included on systems under G3.1.1 exception c requiring turn down at night? I ask because these same spaces in a... Last reply: Tyler Thumma, Feb 17, 2022, 10:12 am |
|
Purchased Condenser WaterNC-v4 EAp2: Minimum Energy Performanceposted by Saif Alsaeed on Jan 7, 2022, 11:50 am
Hello, I am working on a project that has 2 buildings each one will be submitted to LEED as a separate project. The first building is an office building that is served by water cooled self... Last reply: Tyler Thumma, Jan 14, 2022, 11:07 am |
|
Automatic Receptacle Controls- IECC 2018 v ASHRAE 90.1-2010NC-v4 EAp2: Minimum Energy Performanceposted by Cindy Quinn on Jun 4, 2020, 6:08 pm
We are working on a project that has to comply with IECC 2018 in order to meet the city’s energy... Last reply: Jamy Bacchus, Jan 5, 2022, 5:46 pm |
|
Possibility of unconditioned regularly occupied spaceNC-v4 EAp2: Minimum Energy Performanceposted by Alessandro Zuanon on Dec 16, 2021, 6:46 am
Hello, i'm in the case of a regularly occupied space (a mechanical workshop in a warehouse), in which there is the possibility of no heating or cooling system installation. Is it possible... Last reply: Afogreen Build, Dec 21, 2021, 6:01 pm |
|
Baseline Lab SystemsNC-v4 EAp2: Minimum Energy Performanceposted by Cory Duggin on Dec 15, 2021, 12:22 pm
I got a comment on a project that said G3.1.1 exception c means that all qualifying lab spaces would be assigned to one system 5/7 for the whole building not one per floor. Is that correct? Last reply: Tyler Thumma, Dec 20, 2021, 8:28 am |
|
Fine or bulky materialNC-v4 EAp2: Minimum Energy Performanceposted by Francesco Passerini on Jun 10, 2021, 9:10 am
In order to specify the lighting power... Last reply: Dave Hubka, Dec 17, 2021, 3:50 pm |