Commissioning near end of constructionNC-v4 EAp1: Fundamental commissioning and verificationposted by Nadia Azzam on Mar 7, 2024, 10:37 am
We have been handed over a project aiming for LEED Gold that was delayed due to COVID and previously managed by a different LEED admin who has since left the company. After reviewing the... Last reply: Dave Hubka, Mar 8, 2024, 9:33 am |
|
OPR & BOD & Design Document reviewNC-v4 EAp1: Fundamental commissioning and verificationposted by Dave Hubka on Sep 30, 2021, 3:28 pm
Fundamental Commissioning requires the... Last reply: Edgar Arevalo, Aug 9, 2023, 7:03 pm |
|
Question regarding Occupancy sensorNC-v4 EAp1: Fundamental commissioning and verificationposted by Nagaraj Sankar on Dec 29, 2022, 6:47 am
How can we show and prove, here are the palces we gave an ocupancy and daylight sensor for manufacturing project? and Is there gudelines used to follow to place sensor on our drawings ? kindly... |
|
Whether to just upload the Tables of contents for Fundamental Cx documentation review?NC-v4 EAp1: Fundamental commissioning and verificationposted by zz kelvin on Sep 19, 2022, 12:24 pm
When a document is submitted for review, is it understood that only the tables of contents needs to be uploaded, and the detailed document content does not need to be uploaded? In addition, the... Last reply: Dave Hubka, Sep 19, 2022, 12:40 pm |
|
Interpretation of text relating to EnvelopeNC-v4 EAp1: Fundamental commissioning and verificationposted by Keith Fahy on Apr 27, 2022, 7:57 am
Hi, see here an extract from the Reference Guide: "The envelope must be covered in the... |
|
Contractor is not able to comply with Cx SpecificationsNC-v4 EAp1: Fundamental commissioning and verificationposted by Timothy Ian Middleton on Apr 6, 2022, 9:50 pm
We have a project where the contractor is not able to comply with the... Last reply: Timothy Ian Middleton, Apr 7, 2022, 5:51 am |
|
Site Visits for Commissioning Agent?NC-v4 EAp1: Fundamental commissioning and verificationposted by Kasandra Martin on Jan 3, 2022, 12:41 pm
What is the average number of site visits for the Commissioning Agent? It appears a summer and winter for HVAC. One prior to occupancy and then one several months after everything has been... |
|
Potential non-compliance with regulationNC-v4 EAp1: Fundamental commissioning and verificationposted by Timothy Ian Middleton on Dec 8, 2021, 6:13 am
Our... Last reply: Timothy Ian Middleton, Dec 22, 2021, 11:01 pm |
|
On site visits required?NC-v4 EAp1: Fundamental commissioning and verificationposted by Kasandra Martin on Jun 9, 2021, 1:21 pm
The project I am hired to commission is a day drive. Is it possible to only review the contractors tests or is on site necessary or required? Last reply: Dave Hubka, Sep 30, 2021, 2:42 pm |
|
Commissioning Authority's LEED experienceNC-v4 EAp1: Fundamental commissioning and verificationposted by Maria Moran on Oct 28, 2015, 8:17 am
At the Fundamental Commisioning and Verification Prerequisite it says that the... Last reply: Gustavo De las Heras Izquierdo, May 5, 2021, 3:19 am |