When Did the v4 Water Metering Credit Change?

NC-v4 WEc4: Water metering
posted by Kyle G. Pearson on Sep 22, 2023, 12:42 pm

On our last two projects we've gotten a comment indicating that we need to remove the usage of "electric water coolers, janitors sinks, swimming pool, laundry, commercial kitchen, salon sink...

Last reply: Glen Boldt, Sep 28, 2023, 12:28 pm

Reverse Osmosis sumbeter

NC-v4 WEc4: Water metering
posted by Osman Faroq on Jul 17, 2023, 9:29 am

Dear LEED Users, 

I have a doubt about the eligibility of the reverse osmosis sub meters for the credit of water metering. Is the submeter of RO water qualifies and couted as a water...

Last reply: Andrey Kuznetsov, Sep 25, 2023, 5:13 am

Reclaimed water irrigation service metering- can this effectively fulfill quota of (2) minimum water subsystems?

NC-v4 WEc4: Water metering
posted by Joanna Switzer on Feb 14, 2018, 9:08 am

Step 2 of the Step-by-Step BD+C Reference guidance notes...."if the team is using...

Last reply: Kristen Magnuson, Jul 20, 2023, 2:27 pm

Do you need to have landscaping in current design to use landscaping water submeter for this credit? & a question about hot H2O.

NC-v4 WEc4: Water metering
posted by Glen Boldt on Jul 11, 2023, 2:56 am

Our project is a model and protype shop at a private art and design institution. Our first sub-metered water use will be the electric water heater, which provide 100% of the building hot water....

Is "electric water coolers" a drinking water supply equipment

NC-v4 WEc4: Water metering
posted by Jorng-ren Chern on Dec 2, 2020, 9:46 pm

We got this review comment

1. The documentation does not confirm that the non-fixture usage (e.g. electric water coolers and janitors sinks) is measured and can be deducted from the...

Last reply: Karen Joslin, May 17, 2023, 2:40 pm

Metering of chilled water

NC-v4 WEc4: Water metering
posted by on Apr 6, 2023, 5:54 pm

Our project comprises of two buildings- building 1 is existing, building 2 is new. We are only seeking LEED certification for building 2. My questions with regards to water metering requirements...

Number/Location of water meter

NC-v4 WEc4: Water metering
posted by Summer on Jul 21, 2019, 5:14 am

I'm confused if we need to provide the water meter every indoor water fixtures or per floor. Does anyone has experience on this? Thanks.

Last reply: Olga Yuil, Feb 22, 2023, 6:45 pm

Metering of Multiple Boilers (each less than 500,000 Btu/h, but together greater than 500,000 Btu/h)

NC-v4 WEc4: Water metering
posted by Eric Schlichting on Dec 9, 2022, 3:37 pm

Hi,

I had a quick question from my project team looking at water meters on a project. The language of this credit speaks in terms of a single boiler ("boiler of more than 500,000...

Campus approach: can we install water meter for the entire landscape, sanitaryware as a whole

NC-v4 WEc4: Water metering
posted by Michael on Aug 25, 2022, 5:37 am

My project is a campus project, consisting of 4 individual buildings. To fulfill this credit, can I install 1 meter to monitor sanitaryware for 4 buildings together as a whole? or I have to split...

Last reply: Maeve Donohue, Aug 25, 2022, 9:21 am

Water metering Strategy Narrative

NC-v4 WEc4: Water metering
posted by marty seese on Jul 28, 2022, 1:39 pm

Leed online indicates that the documentation needed is a water metering strategy narative. Is this like written text or do drawings work? Just wanting to provide the correct information. We have...

Last reply: Olga Yuil, Jul 29, 2022, 10:46 am