Topic

Local Standards Comparisons as Required Documents

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Nate Shroyer on Jul 27, 2022, 9:10 am

others on this forum who have been through a review of the comparison document recently!  Log in or register to post comments 1 Vote up! ...

Last reply: Emily Purcell, Jul 27, 2022, 10:13 am

Plan de Contrôle d'Erosion & Sedimentation / Storm Water Prevention Plan

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by saif eddine majdaoui on Jul 1, 2019, 10:49 am

Does the monitoring of SWPP and PCES have to be carried out every week on LEED certification projects even if in the absence of rainy / weather events (No precipitation / no rain)

Last reply: Robert Payette, Feb 9, 2022, 11:45 am

What's considered substantial completion if building is completed before the site?

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Adam Huckstep on Jan 25, 2022, 10:37 am

Hi All, I have a question on how to handle a project where construction will continue after the projects building is complete and ready for occupancy.

Background: The project includes a...

Last reply: Emily Purcell, Jan 28, 2022, 10:49 am

SSP1 scope

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Adam Insan on Oct 16, 2019, 11:47 am

Hi, 

We are working on LEED project as general contractor in middle east which is registered under LEED new construction. 

As a part of compliance with SSP1, we have implemented...

Last reply: Jose Gonzalez, Jan 18, 2022, 11:00 am

Zero lot line Definition

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by ed HvacSimulator on Dec 30, 2021, 2:42 am

Hi All!

I read the definition of zero lot line and have a question, does the basement count as construction area?
For example, my building has a basement that takes up the entire...

Last reply: Jose Gonzalez, Jan 9, 2022, 7:05 pm

Soil stockpiling over the winter

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Scott Beckman on Oct 25, 2021, 5:14 pm

We have a correctional project where we are doing some of the sitework now but the project work will be paused over the winter. We will have a soil stockpile and we are concerned about putting a...

Last reply: Emily Purcell, Oct 26, 2021, 4:20 pm

Perimeter Control: is it necessary?

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Victoria Rios Esteve on Oct 4, 2021, 11:04 pm

Hi everyone!

We are working on a LEED v4 New Construction certification of a mall. Renovation only applies to the building, but not to the surrounding parking. Nevertheless, on these ...

Last reply: Emily Purcell, Oct 11, 2021, 10:07 am

LEED Consultants working in remote mode.

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Olga Yuil on Dec 14, 2020, 11:32 am

As LEED Consultants we are working in remote mode because of COVID-19 risk.

The Project Team is concern about how this may or may not affect the certification.

Site visits are...

Last reply: Olga Yuil, Dec 30, 2020, 1:52 pm

IECA vs US EPA CGP

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Gregory Mason on Nov 10, 2020, 8:52 pm

Hi,

We are working on a project outside of the US, and our Civil Engineer has developed their plan in accordance with IECA (International Erosion Control Association) standards. I am...

Last reply: Afogreen Build, Dec 9, 2020, 7:27 am

Activity Pollution Prevention Plan

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Heloise Gaza on May 4, 2020, 12:41 pm

Hello,

We are redoing a recreational park and adding building and splash pads. After 8 months, we realized that we have not done any prevention pollution plan as a...

Last reply: Heloise Gaza, May 12, 2020, 9:59 am