how can attachments (drawings, images) be sent in a CIR?NC-v4 IPc1: Integrative processposted by Sara BENLOUBA on May 25, 2023, 4:45 am
Dear Everybody, We would like to send a... Last reply: Marcus Sheffer, May 25, 2023, 5:47 pm |
|
How contact GBCI for their advice on technical mattersNC-v4 IPc1: Integrative processposted by Sara BENLOUBA on May 24, 2023, 4:59 am
Dear everybody, Please, how do you contact... Last reply: Marcus Sheffer, May 24, 2023, 10:08 am |
|
IP Worksheet- Very confusing languageNC-v4 IPc1: Integrative processposted by Maria Grimm on Jan 23, 2019, 2:55 pm
I'm working on a project where we completed a very thorough IP analysis during concept design. I am finding now, however, that filling out the IP worksheet is extremely painful due to very... Last reply: , May 22, 2023, 2:20 pm |
|
GFA calculation for extremely thick wallsNC-v4 IPc1: Integrative processposted by Filippo Weber on Sep 2, 2022, 4:56 am
Hi, Last reply: Filippo Weber, Sep 2, 2022, 9:37 am |
|
Certification timeNC-v4 IPc1: Integrative processposted by Helena Garcia on Jan 30, 2020, 9:45 am
Hi everyone, Does anyone know if there is a time limit or a deadline from when a project is registered until certification is achieved? Thank you in advance. ... Last reply: Luisa Scambia, Nov 24, 2021, 6:31 am |
|
Pre-selected sites, can a project still opt for Integrative Process credit?NC-v4 IPc1: Integrative processposted by Nermin Hegazy on Jun 20, 2021, 8:50 am
We are studying the feasibility of acheiving LEED certification for a series of floors in an office building. Can the proejct still acheive the Integrative process credit even if the sites... Last reply: Bipin Karki, Jun 23, 2021, 12:40 pm |
|
Project relocated to a new siteNC-v4 IPc1: Integrative processposted by Sara Goenner Curlee on Nov 4, 2020, 1:47 pm
I have a project that just completed the IP credit requirements before the end of SD, and now finds itself likely needing to relocate to a different site. The proposed new site is about 10 miles... Last reply: Sara Goenner Curlee, Nov 4, 2020, 2:21 pm |
|
Integrative process phaseNC-v4 IPc1: Integrative processposted by Marion THIBAULT on Feb 24, 2020, 4:04 pm
Hello, Last reply: Catalyst Partners, Feb 25, 2020, 9:00 am |
|
Simple box modelNC-v4 IPc1: Integrative processposted by Edgar Arevalo on May 1, 2017, 5:49 pm
Ok.... So I'm working on my first LEED v4 BD+C project, and we're looking to pursue the IP credit. As I'm already generating simple box energy model, the requirements state that I target at... Last reply: Oliver Pearce, Oct 11, 2019, 6:08 am |
|
When exactly to submit for this credit?NC-v4 IPc1: Integrative processposted by Sayali G on Sep 13, 2019, 3:37 pm
Hey All, I am very new to the LEED Certification thus just quiet confused about the credit, our firm has just completed 30% of Design Development Phase for a project and were thinking to... Last reply: Sayali G, Sep 16, 2019, 10:38 am |