posted by Ann E on Sep 13, 2018, 8:31 pm

Hi, 

Regarding the mentioned subject, is there/ what papers/certification is needed to submit by the RMC Supplier regarding LEED?

Thank you.

Concrete Formwork

CS-2009 MRc5: Regional Materials
posted by Mike Zupan on Jun 22, 2015, 12:24 pm

Should I include temporary materials, such as concrete formwork and shoring, in the documentation for MRc5?

Thanks!

Last reply: Jon Clifford, Jun 24, 2015, 7:53 pm

Core and Shell Scope & Tenant Scope

CS-2009 MRc5: Regional Materials
posted by Osama Hassan on May 23, 2015, 12:11 pm

Hi, Project is registered on Core & Shell rating System CS V2.0. When i was working on Regional Material Credit MRc5, I found two Options. The First one is Core and Shell Scope & the...

Soil used as filling material can count for MRc5?

CS-2009 MRc5: Regional Materials
posted by Alicia Villanueva on Apr 29, 2015, 1:06 pm

Does the soil used as filling material for the construction can count for MRc5?
It is permanently installed in the building, and the Reference Guide doesn´t mention it as in MRc2 where...

MRc5 Material Tracking/Documentation

CS-2009 MRc5: Regional Materials
posted by Maggie Hogan Skaug on Feb 11, 2015, 11:45 am

RE: usgbc.org/leedonline, CS2009 MRc5
I do not see a form or calculator for material tracking or other forms/upload requirements for this credit documentation. Please advise how this credit...

BDC Material & Resource Calculator- Percentage Regional

CS-2009 MRc5: Regional Materials
posted by Suha Hyderabad on Dec 5, 2014, 3:11 pm

I have a question regarding the BDC Material Tracker, % Regional. The cold formed metal framing Sub says that the steel was manufactured within 28 miles and has been extracted within 74 miles...

Last reply: Jon Clifford, Jan 25, 2015, 3:07 pm

LEED Letter template

CS-2009 MRc5: Regional Materials
posted by Steve Salzman on Apr 28, 2011, 1:39 pm

I am looking for the LEED letter template for CS 2.0 MRc5 (the credit requirements specify that this is necessary in order to capture the credit for the tenant lease/sales option). Is this...

Last reply: Jon Clifford, Jan 25, 2015, 2:21 pm

Regional- Additives Taken into Consideration?

CS-2009 MRc5: Regional Materials
posted by Roberto Meza on Jul 8, 2014, 11:54 am

I have a question regarding the Regional Materials Credit: If a product has
the following components:

- Cement (local product)
- Sand (local product)
- Additives (...

Last reply: RETIRED, Jul 8, 2014, 6:58 pm

MR5

CS-2009 MRc5: Regional Materials
posted by Christine Castellano on Jun 17, 2014, 12:43 pm

Steel sub listed 76.60% of raw materials extracted within 500 miles of project, the data he provided for back-up lists 5 different locations where the...

Last reply: RETIRED, Jun 18, 2014, 12:52 pm

MR5

CS-2009 MRc5: Regional Materials
posted by Christine Castellano on Jun 17, 2014, 12:08 pm

accidentally posted this in MR4 - "this is my first time inputting into LeedOnline - as I cannot find interactive help on that site - I have no idea what to put in the columns where the...

Last reply: Nadav Malin, Jun 17, 2014, 5:02 pm