Is Water considered a recycled material?

CS-2009 MRc4: Recycled Content
posted by Ines Fischer on Apr 22, 2019, 3:44 pm

Hello everyone!

I have some concrete cutsheets where it is specified that 30% of the water used fot it´s mixing was recycled. 

Is water considered as a material for this credit ? if...

Removing "other" costs from total construction cost of project

CS-2009 MRc4: Recycled Content
posted by Edgar Arevalo on Mar 13, 2019, 11:58 am

I am looking at a spreadsheet with the total construction cost for the project.  I already shaved off HVAC, Electrical, Plumbing, and other equipment costs from the total (including audiovisual...

Percentage Range

CS-2009 MRc4: Recycled Content
posted by Edgar Arevalo on Dec 12, 2018, 10:03 am

get-- including BuildingGreen's support of this free forum! As someone volunteering time to answer forum questions, I appreciate it when folks scan the FAQs and other LEEDuser guidance first, so...

Last reply: Tristan Roberts, Dec 12, 2018, 12:08 pm

Default materials cost

CS-2009 MRc4: Recycled Content
posted by Agnieszka Rylska on Oct 25, 2016, 12:52 pm

LEED default materials cost is 45% of total construction costs (based on specific Master Format divisions). What if in a given country we know that materials costs constitute a much higher part...

Last reply: Agnieszka Rylska, Aug 28, 2018, 4:40 am

Paint and coating

CS-2009 MRc4: Recycled Content
posted by Edgar Arevalo on Jan 3, 2018, 4:30 pm

I've been searching through the reference guide but I cannot find a direct answer.  My question is, can we also catalog paints and coatings into the Materials and Resources Calculator?  I've been...

Last reply: emily reese moody, Jan 11, 2018, 7:55 pm

Paints and Coating

CS-2009 MRc4: Recycled Content
posted by Edgar Arevalo on Jan 3, 2018, 4:26 pm

I've been searching through the reference guide but I cannot find a direct answer.  My question is, can we also catalog paints and coatings into the Materials and Resources Calculator?  I've been...

Last reply: Kristina Bach, Jan 4, 2018, 5:09 pm

Total construction cost

CS-2009 MRc4: Recycled Content
posted by Agnieszka Rylska on Jun 30, 2015, 7:05 am

Should the excavation work cost be included in the total contruction cost (while using the default cost of materials equal to 45% of total construction costs)?

Last reply: Tristan Roberts, Sep 13, 2017, 11:01 am

Site Fill as Regional/Recycled Material...

CS-2009 MRc4: Recycled Content
posted by Rick Alfandre on May 23, 2017, 4:06 pm

Looking to confirm:

We are using subgrade Fill for our building project that was procured from an on-site location.

As per the above, site materials can apply to MR 4 and 5...

Last reply: Tristan Roberts, Aug 26, 2017, 7:09 pm

Recycled Water in Concrete and SCMs

CS-2009 MRc4: Recycled Content
posted by Ward Miller on Jun 14, 2017, 11:53 pm

The Reference Guide language related to SCMs in concrete gives project teams the choice whether to include SCMs as a percentage of the entire concrete or separate them out (pg. 373); however, it...

Last reply: Tristan Roberts, Aug 26, 2017, 7:03 pm

Mechanical Insulation

CS-2009 MRc4: Recycled Content
posted by Sarah Gagnon on Aug 2, 2017, 3:25 pm

I know MEP components are not included in the MR4 credit. What about piping or duct insulation? Insulation is part of Division 7, so I say it should be included. My project is the C&S...