Log in
Forum » CS-2009 MRc2
Topic

concrete waste reuse at landfill

CS-2009 MRc2: Construction Waste Management
posted by ST Tan on Jan 20, 2020, 11:22 am

Hi,

We have a project that sent the concrete waste to landfill and the concrete waste is reused as a paving material for a landfill's road. Is it eligible for score for this credit as the...

Last reply: RYAN BEN SABILALA, Jan 23, 2020, 1:24 am

LEED and Safety Officer Duties and Responsibilities

CS-2009 MRc2: Construction Waste Management
posted by Ann E on Mar 4, 2019, 8:52 pm

Hi,

I just want to clarify the difference between waste management (specially housekeeping) of LEED and Safety.

Before LEED program, Safety has been already applied on site and...

Last reply: Adam Insan, Dec 6, 2019, 9:19 am

Conversion

CS-2009 MRc2: Construction Waste Management
posted by Ann E on Feb 26, 2019, 12:50 am

Hi'

Can someone help me how to convert our construction debris volume given in cubic meter to tons?

Every response related is very much appreciated. Thank you.

Last reply: Tiffany Beffel, Mar 4, 2019, 11:01 pm

Clarifications on waste consideration from site office

CS-2009 MRc2: Construction Waste Management
posted by pradeep kumar on Feb 19, 2019, 3:59 am

Hi,

In one of our project, we sent the paper waste from the site office for recycling. Please let us know whether this paper waste from the site office can be considered in the...

Last reply: pradeep kumar, Feb 20, 2019, 7:53 am

waste due to flooding

CS-2009 MRc2: Construction Waste Management
posted by Nicole Isk on Jun 15, 2018, 10:13 am

Dear LEEDers,

during heavy thunderstorms, the municipal combined sewer overflowed and flooded the underground garage at our LEED project site. Unfortunately, building materials that were...

Last reply: Nicole Isk, Jun 21, 2018, 12:26 pm

Co-processing as an approach to Waste Management

CS-2009 MRc2: Construction Waste Management
posted by Katherine Ann Resurreccion on Jun 1, 2017, 2:41 am

Hi All,
I would like to hear your opinion about co-processing as an acceptable...

Last reply: Katherine Ann Resurreccion, Jul 24, 2017, 11:56 pm

Tracking mixed recyclables off-site

CS-2009 MRc2: Construction Waste Management
posted by Maria Luisa Verticchio on Dec 12, 2013, 10:03 am

The job site we are able to begin is inner-city with many restrictions, especially square footage of actual site. There is not enough space to set up multiple bins. Our waste removal provider...

Last reply: Anna Okviana, Oct 10, 2016, 10:15 pm

Reuse of window glass for contstruction fill

CS-2009 MRc2: Construction Waste Management
posted by Maria Glädt on Apr 15, 2016, 6:12 am

We're involved in a Project where the Contractor wants to send the window glass to a facility that crushes the glass. The crushed glass material can after this be used as construction fill for...

Last reply: RETIRED, Apr 15, 2016, 9:02 am

Waste management pro-rate surface logic for two buildings

CS-2009 MRc2: Construction Waste Management
posted by Ian McCall on Jun 16, 2015, 11:48 am

calculation at the end of the job and will not affect logistics on the job site. See also our discussion on NC Forum- http://www.leeduser.com/credit/NC-2009/MRc2?all-comments=true#comment-57828. Let us know...

Last reply: Ian McCall, Jun 17, 2015, 12:39 pm

Construction Waste Diversion vs Material Re-Use

CS-2009 MRc2: Construction Waste Management
posted by Tim Gaidis on Feb 20, 2015, 1:11 pm

Hi all, I'm working on a LEED-NC v3 major renovation project that has veered just below it's 50% MRc2...

Last reply: Tim Gaidis, Feb 20, 2015, 5:20 pm