Forum » CS-2009 EAc6
Topic

Core and Shell area and Tenants area

CS-2009 EAc6: Green Power
posted by Vassil Vassilev on Nov 30, 2021, 11:02 am

Greetings,

Pursuing EAc6, Option 1, for office building registered as C&S for LEED certification, the following issue is kind of not clear to me:

Normally, when a building type...

Last reply: Marcus Sheffer, Dec 2, 2021, 10:19 am

Electricity usage x gross square footage

CS-2009 EAc6: Green Power
posted by Adriana Hansen on Jan 11, 2011, 1:09 pm

Hello,

I have a Core and Shell building under certification that has 5 underground parking floors. According to LEED Reference Guide, page 612, "projects which contain underground and/or...

Last reply: Devendra Chaughule, Jul 27, 2021, 9:21 am

Project with PV- Calculating Green Power?

CS-2009 EAc6: Green Power
posted by Brian Salazar on Oct 15, 2019, 1:04 pm

Hello!  I am working on a project with on-site PV.  When calculating the Green Power offset, do we need to offset the total modeled electricity usage BEFORE or AFTER subtracting the electricity...

Last reply: Brian Salazar, Oct 15, 2019, 1:39 pm

Net Zero Building

CS-2009 EAc6: Green Power
posted by Lisa Marshall on Jan 19, 2015, 6:29 pm

Hello, my project is going for Net Zero energy consumption and we were planning on going for the EAc6 - Green Power credits. Can I take automatic credit for EAc6 and and Innovation credit, just...

Last reply: Paula Melton, Nov 8, 2018, 9:44 am

Green Power-contract / purchase date

CS-2009 EAc6: Green Power
posted by C. Anthony Menefee on May 31, 2011, 2:04 pm

Is it possible for the owner to sign the 2 year contract and begin energy consumption before the building is completed and occupied?

Last reply: Marcus Sheffer, Feb 2, 2018, 6:07 pm

Purchasing RECs for Projects with District Cooling

CS-2009 EAc6: Green Power
posted by Katherine Ann Resurreccion on Jul 25, 2017, 11:12 pm

Hi, we have a LEED 2009 registered Core and Shell project in the Philippines which utilizes district cooling. We are to pursue EAc6: Green Power by purchasing RECs, and calculate annual...

Last reply: Marcus Sheffer, Jul 28, 2017, 12:03 pm

owner/tenant contract

CS-2009 EAc6: Green Power
posted by FABIO VIERO on Feb 15, 2017, 4:34 am

Hi all,
we are working on a shell&core project that, once completed, will be a single tenant occupied buiding. The Owner would like to ask the tenant to manage and sign the eletricity...

Last reply: Marcus Sheffer, Feb 22, 2017, 9:28 am

Option 1 or Option 2

CS-2009 EAc6: Green Power
posted by Martin Meehan on Jan 27, 2017, 5:00 am

Hello all,

I am working on a Core and Shell project that is targeting Green Power. While we have an energy model for the project, can you confirm if the project MUST use the Option 1? Or...

Last reply: Marcus Sheffer, Jan 27, 2017, 9:48 am

Community Choice Aggregation (CCA)

CS-2009 EAc6: Green Power
posted by Megan White on Oct 26, 2016, 12:52 pm

Do we know if...

Last reply: Marcus Sheffer, Jan 19, 2017, 9:27 am

Off-Site Solar Used to Power 100% of Building Electricity

CS-2009 EAc6: Green Power
posted by Heather South on Aug 12, 2015, 12:35 pm

I am working on a LEED CS 2009 project and the owner of the building is building an off-site solar farm in a different town in the same state as the building he also owns and is going to be...

Last reply: Tristan Roberts, Aug 21, 2015, 10:18 am