Topic

Core & Shell without HVAC or electrical systems

CS-2009 MPR2: Must be a complete, permanent building or space
posted by Celia Puertas Romero on Jul 13, 2016, 8:42 am

We would like to pursue LEED Core & Shell certification for a building undergoing a major renovation. The scope of the owner´s Project includes renovation of the facade, and demolition of...

Multiple Building or One Building?

CS-2009 MPR2: Must be a complete, permanent building or space
posted by Muge Karasahin on Aug 28, 2015, 2:29 pm

We have a large scale international project, consists of five attached building blocks (A-B-B1-B2-C) that share 7 basement and 7 ground up floors but each have different amount of total floor...

CS MPR2: reclaimed land without development previously

CS-2009 MPR2: Must be a complete, permanent building or space
posted by Vivien Wong on Jul 9, 2014, 3:13 am

Dear Tristan,
If a project is located in a reclaimed land which without previous development (i.e.: the project will be the first development in the reclaimed land), can still meet the...

how long can be interval time between 2 parts of projects

CS-2009 MPR2: Must be a complete, permanent building or space
posted by Catharina B on Mar 30, 2014, 3:15 pm

Hello
We are working on the project, which include 3 independent buildings: A, B & C – but for certification is one single building (each 17 stories above grade has own mechanic, energy...

AGMBC: Multiple Building and On-Campus Projects

CS-2009 MPR2: Must be a complete, permanent building or space
posted by Tam Kin Hung on Mar 19, 2014, 4:28 am

Project brief:
1. The project is composed of 3 office buildings with retail podium for each of them, 1 residential building also with retail store surrounding it.
2. All the buildings...