Topic | Recent |
---|---|
Temperature and Humidity Monitoring During FlushCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Nancy Henderson on May 22, 2012, 5:33 pm
Is it part of the requirement of this credit to monitor temperature and humidity in the space during the flush out - or is it sufficient to provide the temperature set points and calculate the... Last reply: Jose Antonio Kovacevic, Mar 13, 2018, 11:01 am |
|
Option 2 IAQ Testing- ScheduleCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Anne-Claire BARBERI on Jun 25, 2015, 12:48 pm
Hello, In the reference guide, it is written that for "Option 2 Air Testing", the test must be conducted after construction ends and within 14 days following occupancy. Moreover, the test... Last reply: Akos Brandecker, Jun 24, 2016, 5:52 am |
|
Building Flush- Filter Change?CI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Brianne Smith on Apr 4, 2016, 5:01 pm
Our project is pursuing Option 1 Path 2 - Flush During Early Occupancy. Do filters need to be replaced after the flush, or only after construction as part of IEQc3.1? Last reply: Dave Hubka, Apr 5, 2016, 1:12 pm |
|
IAQ TestingCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Brett Farbstein on Apr 29, 2014, 2:13 pm
Can the Owner or... Last reply: Akos Brandecker, Jul 22, 2014, 7:18 am |
|
Question on Selecting IAQ Test LocationsCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Melissa Wrolstad on Feb 6, 2012, 2:25 pm
I am working on a small ~6,500 sq. ft. LEED-CI office space. The space is served outdoor air from a single... Last reply: Tristan Roberts, Nov 3, 2013, 11:26 pm |
|
IAQ testing in a continuously occupied officeCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Maggie Edelstein on Aug 19, 2013, 1:26 pm
Our project is a government office that will be continuously occupied throughout the duration of construction. (Workers will move to a different office or cubical on the day(s) that their space... Last reply: Dylan Connelly, Sep 3, 2013, 5:47 pm |
|
Is flush out possible in countries with high humidity?CI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Katherine Ann Resurreccion on Aug 27, 2013, 11:56 pm
Hi, we would like to know if flush out is practicable in areas where high humidity is experienced whole year, say 70-85%. Should we cancel out option 1 already and go for option 2 (... Last reply: Dylan Connelly, Sep 3, 2013, 5:46 pm |
|
outdoor delivery rates in a naturally ventilated spaceCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Vera Voropaeva on Jan 8, 2013, 6:20 pm
After receiving the project's review we are asked to provide outdoor delivery rates. The project was flushed out with a 2,000 CFM fan for 48 hours with windows and a door open providing a... Last reply: Tristan Roberts, Mar 21, 2013, 3:39 pm |
|
Number of IAQ Sampling Locations in Apartment Building?CI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Bill Kilpatrick on Dec 20, 2012, 12:00 pm
I would appreciate advice on the number of sampling locations needed for LEED Testing per IEQ Credit 3.2 Option 2 in mid-rise Apartment buildings. We follow the sampling rules for... Last reply: Tristan Roberts, Mar 21, 2013, 3:32 pm |
|
Combining Option A and BCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by William Thompson on Oct 3, 2011, 1:20 pm
Can Options A and B be combined? Someof the floors are occupied and have met Option B testing requirements. But now the project schedule has changed and we're concerned that fast-tracking the... Last reply: Vince Briones, Nov 28, 2012, 6:51 am |