Topic

Temperature and Humidity Monitoring During Flush

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Nancy Henderson on May 22, 2012, 5:33 pm

Is it part of the requirement of this credit to monitor temperature and humidity in the space during the flush out - or is it sufficient to provide the temperature set points and calculate the...

Last reply: Jose Antonio Kovacevic, Mar 13, 2018, 11:01 am

Option 2 IAQ Testing- Schedule

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Anne-Claire BARBERI on Jun 25, 2015, 12:48 pm

Hello,

In the reference guide, it is written that for "Option 2 Air Testing", the test must be conducted after construction ends and within 14 days following occupancy. Moreover, the test...

Last reply: Akos Brandecker, Jun 24, 2016, 5:52 am

Building Flush- Filter Change?

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Brianne Smith on Apr 4, 2016, 5:01 pm

Our project is pursuing Option 1 Path 2 - Flush During Early Occupancy. Do filters need to be replaced after the flush, or only after construction as part of IEQc3.1?

Last reply: Dave Hubka, Apr 5, 2016, 1:12 pm

IAQ Testing

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Brett Farbstein on Apr 29, 2014, 2:13 pm

Can the Owner or...

Last reply: Akos Brandecker, Jul 22, 2014, 7:18 am

Question on Selecting IAQ Test Locations

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Melissa Wrolstad on Feb 6, 2012, 2:25 pm

I am working on a small ~6,500 sq. ft. LEED-CI office space. The space is served outdoor air from a single...

Last reply: Tristan Roberts, Nov 3, 2013, 11:26 pm

IAQ testing in a continuously occupied office

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Maggie Edelstein on Aug 19, 2013, 1:26 pm

Our project is a government office that will be continuously occupied throughout the duration of construction. (Workers will move to a different office or cubical on the day(s) that their space...

Last reply: Dylan Connelly, Sep 3, 2013, 5:47 pm

Is flush out possible in countries with high humidity?

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Katherine Ann Resurreccion on Aug 27, 2013, 11:56 pm

Hi, we would like to know if flush out is practicable in areas where high humidity is experienced whole year, say 70-85%. Should we cancel out option 1 already and go for option 2 (...

Last reply: Dylan Connelly, Sep 3, 2013, 5:46 pm

outdoor delivery rates in a naturally ventilated space

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Vera Voropaeva on Jan 8, 2013, 6:20 pm

After receiving the project's review we are asked to provide outdoor delivery rates.

The project was flushed out with a 2,000 CFM fan for 48 hours with windows and a door open providing a...

Last reply: Tristan Roberts, Mar 21, 2013, 3:39 pm

Number of IAQ Sampling Locations in Apartment Building?

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Bill Kilpatrick on Dec 20, 2012, 12:00 pm

I would appreciate advice on the number of sampling locations needed for LEED Testing per IEQ Credit 3.2 Option 2 in mid-rise Apartment buildings.

We follow the sampling rules for...

Last reply: Tristan Roberts, Mar 21, 2013, 3:32 pm

Combining Option A and B

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by William Thompson on Oct 3, 2011, 1:20 pm

Can Options A and B be combined? Someof the floors are occupied and have met Option B testing requirements. But now the project schedule has changed and we're concerned that fast-tracking the...

Last reply: Vince Briones, Nov 28, 2012, 6:51 am