Topic | Recent |
---|---|
100% Outside Air systemsCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Christie Rimes on Sep 1, 2015, 9:49 pm
The... Last reply: Dylan Connelly, Sep 10, 2015, 7:37 pm |
|
temporary capping of the remaining duct workCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Megan Bove on Jul 28, 2015, 2:58 pm
If there is a project that is going to demo 1/2 of the ductwork on a floor site hich the building is keeping on the HVAC System during construction do we need to put temporary capping of the... Last reply: Michelle Halle Stern, Aug 11, 2015, 5:56 pm |
|
Cleaning Requirements for bathroom demoCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Megan Bove on Mar 17, 2015, 8:43 am
If there is a CI project that has an existing bathroom that is set to be demolished as other build outs are happening, are there specific... Last reply: Michelle Halle Stern, Mar 17, 2015, 9:28 am |
|
Ductwork cleaningCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Megan Bove on Dec 9, 2014, 8:21 am
Hi. If when inspecting a LEED job-site and you find that ductwork is without covering/blue film, I know that cleaning out the dust must occur. My question is there specific requirements for a... Last reply: Michelle Halle Stern, Dec 9, 2014, 11:53 pm |
|
Wet mineral wool on spandrelCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Antonio Rodriguez on Mar 21, 2013, 11:17 am
I am working on an office tower project in Panama, and rain season is about to begin. What should we do if the mineral wool used for insulation on spandrels should get wet? Most of it is already... Last reply: Tristan Roberts, Nov 3, 2013, 11:27 pm |
|
Pre Occupancy Filter Replacement for a TenantCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Laura Charlier on Jun 24, 2011, 1:46 pm
Is a CI project required to replace the filters of the main building... Last reply: Jackie Mustakas, Nov 26, 2012, 5:25 pm |
|
Exposed duct insulation in open return plenum IAQ concern?CI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Greengrade User on Jul 24, 2012, 3:36 pm
We are trying to achieve LEED CI v2009 Certification. The project is a 6,237 SF office space tenant in a 336,510 SF building occupying approximately 50% of the 11th floor. We are 3 weeks into... Last reply: Dylan Connelly, Sep 7, 2012, 6:18 pm |
|
Carpet Material??CI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Jan Senica on Mar 19, 2012, 12:36 pm
We wanted to know if you could please help us out with the carpet material. Last reply: Yetsuh Frank, Jun 25, 2012, 3:52 pm |
|
MERV Filter ReplacementCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Sheela I on Mar 21, 2012, 10:45 am
Prior to demo/During construction we have installed... Last reply: Yetsuh Frank, Jun 25, 2012, 3:45 pm |
|
IAQ Concerns due to LEED boundaryCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Kunjan Shah on Feb 1, 2012, 5:03 pm
My project is inside a 3 story building. The remodel work spans all 3 floors and City permit drawings show work all over the building and building shell. My client wishes to restrict the LEED... Last reply: Tristan Roberts, Feb 21, 2012, 9:16 pm |