AAMA ratings for U-Value vs. NFRC ratings

NC-2009 EAp2:Minimum energy performance
posted by  Douglas Flandro  on 

Our rep has given us AAMA ratings to determine the U-Value of the curtain wall assemblies. LEED seems to be asking for NFRC ratings. Do we need to insist on the NFRC ratings?

4
Sustainability Enabler
Eskew+Dumez+Ripple
LEEDuser Basic Member
20 thumbs up
Wed Mar 13, 2019, 2:37 pm

Does low-emitting and fuel efficient vehicles parking count as preferred parking?

CI-v4 LTc5:Reduced parking footprint
posted by  Ameet AA  on 

Hi,

 

Our project has a few parking spaces reserved for low-emitting and fuel efficient vehicles, does it count as preferred parking? Thanks.

0

Scope of credit

CS-v4 EQc3:Construction indoor air quality management plan
posted by  ilse angel  on 

During construction there is an stage when the contractor is building the slabs and columns of the levels above the ground floor.

1
Tue Mar 12, 2019, 10:09 pm

Energy Modelling - Baseline water-cooled chiller's COP, adjusted to local outdoor conditions in lieu of AHRI conditions?

CI-v4 EAc2:Optimize energy performance
posted by  Andrew Xiao Junzhao  on 

Dear LEED APs,

I have a LEED CI v4 project in Taipei, Taiwan, which require whole building energy modelling. Couple of questions I hope to seek clarity:

 

1
Mon Mar 18, 2019, 7:46 pm

Reuse furniture cost

CI-v4 MRc2:Interiors life-cycle impact reduction
posted by  pradeep kumar  on 

We are doing the project in which our client reusing the furniture from their existing office to the new office. Furniture comprises of wooden tables, chairs etc.

0

Watersense products

NC-v4 WEp2:Indoor water use reduction
posted by  Reshadee Weerasooriya  on 

When a project outside US cannot find equivalent listed, is it enough just to meet the specified 20% reduction requirements?

4
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Tue Mar 12, 2019, 3:10 am

Flush Out Path 2 - Fitness center/ Office

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Crina Bosch   on 

I am working on a fitness center project and the team would like to follow Enhanced Commisioning Path 2: Flush-out.