Dear concern
We are working in a huge industrial project without any lighting controls such as dimming control , Occupancy sensor and time relay
Our clarifications are
1.Is there any mandatory requirement for lighting in proposed case
2.can I consider mandatory requirement only in basecase ( in reality no lighting controls available in project )
3.is the project not qualified for if we don't have lighting controls
SAMY Chamy
EnginneerT&T Green
12 thumbs up
March 17, 2019 - 11:42 pm
Awaiting for the reply
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
March 18, 2019 - 3:09 pm
1. Yes the mandatory provisions include some for lighting see Section 9.4.
2. No
3. Projects must meet the mandatory provisions to qualify for this prerequisite.