Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Existing Chiller in 100% building construction refurbishment

CS-2009 EAc1:Optimize Energy Performance
posted by  heinrich post  on 

I am wondering how to handle an existing chiller in a LEED C&S project. The building of the C&S project got 100% refurbishment for the building constructions. The central chiller plant has

7
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Mar 6, 2012, 2:39 am
3
Tue Mar 6, 2012, 1:34 am

M&V for C&S buildings of varying occupany when complete

CS-2009 EAp2:Minimum Energy Performance
posted by  Tony Schafer  on 

I have another question related to my last one regarding M&V and the energy model.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Mar 5, 2012, 5:32 pm

peak flow calculations for 24-hr duration

NC-2009 SSc6.1:Stormwater Design—Quantity Control
posted by  Chris Olson  on 

Hello - My question is in regards to the 2-yr, 24-hr requirement for calculating peak runoff rate.

2
Sustainability Manager
KEMA Services
LEEDuser Basic Member
110 thumbs up
Mon Mar 5, 2012, 1:23 pm

How to quantify a evaporation rate

NC-2009 SSc6.1:Stormwater Design—Quantity Control
posted by  Brian Lodes  on 

I was hoping I could get some advice on obtaining the quantity requirement of SS CR 6.1. We are trying to obtain this credit on an approximate 19 acre site.

3
Mon Mar 5, 2012, 2:31 am

green roof

NC-2009 SSc6.2:Stormwater Design—Quality Control
posted by  Emmanuel Pauwels  on 

We will install an extensive green roof in our project. Does anyone know what the runoff rarte is and how much TSS are captured by 2.7 inches of substrate?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Sat Mar 3, 2012, 2:34 pm

TSS removal efficiency % table?

NC-2009 SSc6.2:Stormwater Design—Quality Control
posted by  Kash Boodjeh  on 

What is the best resource for finding TSS removal efficiency for various BMPs? Is there a table or reference to base our #s off of since we don't have calculations or on-site monitoring?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Sat Mar 3, 2012, 2:17 pm

Core & Shell M&V

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Randy Cook  on 

Hello, I have read thru the previous posts and responses, and hope this is not a redundant question. I am working on a C&S major renovation. We are going to follow Option B from IPMVP Vol.3.

3
Default Avatar
Associate Director
The Rock Brook Consulting Group
LEEDuser Basic Member
6 thumbs up
Fri Mar 2, 2012, 10:13 pm

Design or Construction Credit?

Pilot-Credits EQpc24:Acoustics
posted by  Orlin Velinov, PE  on 

Is this s design or construction credit? From the credit form requirements looks like the NC levels will have to be measured, the rest criteria can be theoretically analysed or modeled.

3
Fri Mar 2, 2012, 7:45 pm

Parking Capacity overflow to Gravel Lot

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Eduardo Guzman  on 

We have a research building that shares an asphalt parking lot with a warehouse (used by the researchers but not being certified).

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Fri Mar 2, 2012, 5:46 pm