Forum quick links
Window Film Adhesive
CI-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Jessica Aubert on
We are working on a CI project which is bounded on three sides by a glass atrium space.
Commissioning of Systems not required in prereq
NC-2009 EAc3:Enhanced Commissioningposted by Shauna Sproul on
Can points be achieved in innovation and design for commissioning of systems not required in prereq, for example the building envelope? I understand 2012 is addressing this, but what about 2009? I
CxA designation question
NC-2009 EAc3:Enhanced Commissioningposted by Blas Beristain on
Hello! We are involved in a project of a new headquarters of an architectural firm. In this project, the owner will be the architectural firm.
CxA Contract Question
NC-2009 EAc3:Enhanced Commissioningposted by Mark Haynie on
We hold a contract for construction of a project as the General Contractor. We also have contracted with the design firm (Architect) for the project.
Round-up
EBOM-2009 SSc3:Integrated Pest Management, Erosion Control, and Landscape Managementposted by SIG - Sustainability Main Account on
I'd like to confirm that Round-Up Pro (EPA # 524-475) is okay to use for weed control in sidewalk cracks.
All indoor water is outside of project owner scope
CS-2009 WEp1:Water Use Reductionposted by Mary Frances Stotler on
I'm trying to figure out how to document compliance with WEp1 and WEc3. I'm dealing with a situation where all indoor water use is part of the tenant build-out.
Secure bicycle racks and secure bicycle storage
CS-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Caroline Ma on
Any difference between Secure bicycle racks and secure bicycle storage? In CS project with area larger that 300,000 sq.ft. (CS case 2), we need to provide secure bicycle storage.
No Engineer on Project
CI-2009 IEQp1:Minimum IAQ Performanceposted by Paul Meyer, PE, CEM, CBCP, GBE LEED AP on
All HVAC mechanical systems were existing. Only the ductwork was installed. There is Engineer for this project is there a way to comply without the signature?
Steel Joists & Deck
NC-2009 MRc5:Regional Materialsposted by Jeremy Hatfield on
I am a bit confused when it comes to Steel Joist and Deck. New Millennium and Vulcraft obtain steel from mills.
Stated Cost
NC-2009 MRc5:Regional Materialsposted by matthew convery on
When calculating both the regional material and recycled content material percentages, do you use the subcontractors cost or can they include their markup?