Dear all,
We're developing an M&V Plan for a large commercial mall. Every tenant will be equipped with an electricity submeter, connected to the Mall's BMS.
The tenants will be billed according to their consumption recorded on their submeters. Tenants can access the BMS room to check their instantaneous energy consumption, but only after requesting this from the Facility Manager. In other words, tenants' access to their energy consumption is possible but not easy.
Is there a requirement for this EAc5.2 requiring the tenants to have direct & easy access to their energy consumption, at any time they desire?
Thanks,
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
February 21, 2012 - 11:11 pm
George, not exactly but there is a requirement to "Develop a tenant measurement and verification (M&V) plan that
documents and advises future tenants of this opportunity and the means
of achievement."
Shannon Allison
Project EngineerIntegral Group
35 thumbs up
April 30, 2012 - 4:08 pm
Tristan,
Is there an example of a tenant M&V plan? There is not a lot of guidance on this requirement.
Emily Catacchio
Sustainability SpecialistWight and Company
610 thumbs up
May 8, 2012 - 6:13 pm
Shannon,If you look under the resources tab, there isn't a specific example, but plenty of guidelines to put one together!