Changing and Shower facility
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Hanne Goa on
According to Leed NC we require for 911 FTEs x 0,5% = 4,6 Changing and Shower facilities (=5).
what can be included in LEED project boundary?
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Adam Targowski on
The owner has a land which is divided into 3 parts.
LEED Project Boundary/Parking
NC-2009 PIf1:Minimum Program Requirementsposted by renee jimenez on
We are designing a Triple A ballpark on a parcel of land owned by the City approx.
Doubt about the Budget System type
CI-2009 EAp2:Minimum Energy Performanceposted by Rodrigo Dias on
Hello I'm simulating a store to the LEED CI cetification and using the section 11 to create the Budget Building Design.
Do I have to install plumbing fixtures?
ND-v2009 GIBc3:Building water efficiencyposted by Fang Wang on
We have a residential project in China, the owner is interested in getting LEED ND certified.
5th bullet of the Ref Guide
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Marcio Alberto Casado Pereira on
Dear all, We don't quite understand what this means: "An alternative compliance path using FloorScore is acceptable for credit achievement: 100% of the non-carpet finished flooring must be FloorSc
Particulate Matter Removal
NC-2009 IEQp1:Minimum IAQ Performanceposted by Paula Hernandez on
Hi, We are still having problems to install MERV 6 filters upstream VRF evaporators cooling coils, due to the low pressure they can give and luck of enough space to place them. What if we install s
Electric Cigarettes
NC-2009 IEQp1:Minimum IAQ Performanceposted by Andreas M. Roessler on
Dear all, one of our major clients set an interesting question concerning electronic cigarettes. In the building we already certified smoking is not allowed, but could be electronic cigarettes?
Will alterations to entry vestibule qualify for MRc3?
EBOM-2009 MRc3:Sustainable Purchasing—Facility Alterations and Additionsposted by Julie Pollack on
During the performance period for LEED EBOM, the building owner is remodeling the main entrance vestibule to the project building. The vestibule is a separate, enclosed space of 263 sq ft.
Using treated seawater for landscaping
EBOM-2009 WEc3:Water Efficient Landscapingposted by Vincent Kotwicki on
The intent of the credit says "To limit or eliminate the use of potable water or other natural surface or subsurface resources available on or near the project site for landscape irrigation." I ha