Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

View answers »

Forum discussion

CS-2009 EAp2:Minimum Energy Performance

Undefined Outdoor Spaces and Exterior Lightning

Greetings Everyone I'm working on a office project with outdoor spaces within the LEED Boundary. The project's construction phase is almost finished. Originally this was going to be the only building in the project, but during construction, the owner bought the adjacent land and decided to build a second building which is still on early design phase. Originally a design for the outdoor spaces was made by the architects, but the owner idea is that both building will be part of a same development and will share some of their outdoor spaces. Therefore, the design and construction of some of these spaces have been halted and will resume when the second building's construction begins. This includes the design for the exterior lightning of this space. Since the space I'm speaking about are inside my project's LEED project boundary, but their design will not be defined until some time in the future I don't know how to account for it in this and other credits. Should I exclude this space from the boundary? Should I assume an exterior illumination design that complies with ASHRAE's LPD requirements but doesn't achieve further savings? Should I assume the original design? This situation also affects other credits, and I don't know how to approach it. Any ideas? Thanks in advance for your help.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 01/30/2013 - 15:04

The boundary issue needs to be resolved for the entire submission before you can determine the appropriate way to deal with it. Two guiding principles to consider - always model the proposed as it was constructed and the baseline in many instances varies depending on the proposed. Ultimately you will need to either exclude it (if possible) or model it as it was finally constructed.

Wed, 01/30/2013 - 15:11

Marcus, thank you very much for your answer, it's been really helpful. Most probably what will do is exclude that area from the LEED boundary for this project, and include it in the LEED boundary for the second building of the development. By the time the second building is finished, construction in the undefined area will also be over.