overall accuracy, anticipated areas of error susceptibility

NC-2009 EAc5:Measurement and Verification
posted by  Leanne Niu  on 

There is a review comment in my project as follows: It appears that the M&V plan provided does not specify the expected overall accuracy, anticipated areas of error susceptibility, and magnitud

3
Default Avatar
AECOM
LEEDuser Basic Member
0 thumbs up
Tue Mar 14, 2017, 6:28 pm

New materials and resources calculator since 12/01/16

NC-2009 MRc5:Regional Materials
posted by  Guillermo Brunzini  on 

Hello Everybody, Two questions: 1- a project registered in 2012 can use the new materials and resources calculator? 2- What happens with the cutsheets required in previous versions,?

2
Default Avatar
LEED Consultant
The Green Engineer
LEEDuser Basic Member
188 thumbs up
Tue Mar 14, 2017, 3:55 pm
4
President
HJKessler Associates
LEEDuser Basic Member
41 thumbs up
Mon Mar 13, 2017, 10:01 pm

Local voluntary cleanup program - definition

NC-2009 SSc3:Brownfield Redevelopment
posted by  Anna Korinkova  on 

Under Option 1 of the credit, we can pursue EITHER the ASTM E1903-97 Phase II Environmental Site Assessment OR the 'local voluntary cleanup program'.

3
Mon Mar 13, 2017, 4:52 pm

Which flooring system in project scope must be compliant?

CS-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Alessio Zampaglione  on 

Hi everyone, I’m working on an office building project registered under LEED C&S2009 in which there are different flooring systems: .

6
Mon Mar 13, 2017, 3:00 pm

Section 3.10 compliance

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Edgar Arevalo  on 

I'm working on a CI project that we are currently designing VAVs for the floor(s), the main AHUs are not part of the scope of work but they have VFDs.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Mar 13, 2017, 1:30 pm

Interior paint's VOC

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Magda Aghababyan  on 

According to Green Seal Standard GS-11, Paints, 1st Edition, May 20, 1993 the VOC limit for interior flat paint is 50 grams/liter of product minus water.

2
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Mon Mar 13, 2017, 5:04 am

Air testing related to partial renovation per floor

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Julie Barth  on 

I have a client who is asking about air testing for an office building renovation project where small parts of each floor will be renovated.

4
Default Avatar
Industrial Hygienist
Aria Environmental, Inc.
LEEDuser Basic Member
1 thumbs up
Sat Mar 11, 2017, 12:44 am

Help with LEED ND

ND-Plan-v4 MPR1:Must be in a permanent location on existing land
posted by  T J  on 

I'm a beginner and not familiar with the certification process and actual documentation. Where can I get samples or ideas on how to to begin making a simple LEED-ND assessment report including chec

7
Default Avatar
LEEDuser Basic Member
0 thumbs up
Thu Mar 9, 2017, 7:11 pm

Laboratory

NC-v4 WEp2:Indoor water use reduction
posted by  Vanessa Montezuma Ramos  on 

My project is an Investigation Center which has laboratories. The lavatories found in the lab area (chemistry) should be considered in this credit?

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Thu Mar 9, 2017, 3:13 pm