EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Izabela Kwiecinska on
Hi Everyone, We are working on a building that already got LEED C&S certificate in 2012 and now aims to get EBOM.
Level II audit
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Robert Calloway on
If you go the Level II route (in lieu of RCx), does uploading a level II audit for the level I audit suffice?
Am i required to do the Level I first
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Chris Callas on
We are looking to do this in-house, we can document the study and record the findings. but as part of this credit do i need to show i performed the Level I first?
Minimum number of equipments to be audited
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by ESD Singapore on
Hi all, The project that we are working on would like to go pursue this credit using ASHRAE level 2 commissioning audit path. However, this project has a large quantity of AHUs and FCUs (approx.
Retrocommissioning - Systems Requirements
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Nate Eppley on
I am working on a cultural center performance space in San Diego with very few HVAC system components.
Existing Building Commissioning
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by sebastian castañeda on
Hello. I am a student who is interested in learning about the methodology of LEED certification and there are some points that I do not clear.
Timing of ASHRAE Level I & II & BAS System Install
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Marie Kirk on
We are going for LEED EBOM v 2009 and need to finish the process by Spring 2017. An engineering firm is getting ready to do an ASHRAE Level I & II audit for us to receive the EA Credit 2.1.
Advises about an orientation in the all project.
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Andres Giraldo on
Hi LEED, we have started the process of LEED EBOM certification in Aug-2013, the facility is categorized as industrial/manufacturing.
Occupant service capabilities
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Magda Aghababyan on
Hi, Reviewer comment asks us to provide "The effect on occupant service capabilities" of the capital measures identified during the level II audit.
Audits Around the World
EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysisposted by Jenny Carney on
All, I'm trying to compile a list of energy audit providers outside of the US.