OK, so.....if I haven't done any updates to the building in the 24 months prior to application for EBOM, then it's impossible to get EAc2.3, no matter how much the company might invest immediately AFTER application, is that right?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
530 thumbs up
April 29, 2014 - 3:59 pm
It is likely that only projects pursuing EACredit 2.1, Option 1 will be eligible to achieve EAc2.3. EAc2.3 does not add commissioning work to EAc2.1 but rather emphasizes timing and integration of commissioning into the facility's standard procedures.
Building updates are not a requirement to achieve either EAc2.1 or EAc2.3.