Construction IAQ management plan - before occupancy
Filter by location
Forum
Topic
Replies
Recent

Apparatus Bay Flush out

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Richard Naldrett  on 

We have a Fire Station project scheduled for a flush out of the Appratus Bay. The space has heating but there is not a simple way to control humidity.

1
Wed Sep 18, 2013, 3:41 pm

IAQ Flush out-using temporary exhaust systems

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Stella Stella  on 

Hi, We are proposing a IAQ flush out procedure for our facility which consist of a lot of FCU’s. Due to the FCU’s the flush out procedure is excessively long.

0

Implementing IAQ testing shell space

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Summer Minchew  on 

Noting that an equivalent to IEQc3.2 is not available within the LEED-CS rating system, is it safe to assume that future tenant space(s) within a LEED-NC project would not be subject to IAQ testing

3
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Tue Aug 1, 2017, 10:59 pm

Air testing related to partial renovation per floor

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Julie Barth  on 

I have a client who is asking about air testing for an office building renovation project where small parts of each floor will be renovated.

4
Default Avatar
Industrial Hygienist
Aria Environmental, Inc.
LEEDuser Basic Member
1 thumbs up
Sat Mar 11, 2017, 12:44 am

Number of air testing samples

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Qian Tang  on 

Our project office building has 22 floors and is divided in 4 portions – north wing, south wing, east wing and west wing.

3
Default Avatar
President
Indoor Sciences, Inc.
LEEDuser Basic Member
0 thumbs up
Wed Jan 18, 2017, 7:04 pm

Questions.

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  ethen mcmanus  on 

Listed below is my list of questions: A) We have several FRESH air handling units and REGULAR air handling units on the roof of our building.

3
Building Enclosure Consultant
BPL Enclosure
LEEDuser Basic Member
58 thumbs up
Tue Jan 10, 2017, 9:04 pm

Combine options

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Leandro Silva  on 

We are certifying a Project and we are preparing the documentation for the EQ credit 3.2 Construction Indoor Air Quality Management Plan – Before Occupancy.

3
Default Avatar
Project Manager
McKissack and McKissack
LEEDuser Basic Member
0 thumbs up
Thu Sep 1, 2016, 1:54 pm

Maximum Temperature

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Omar Elrawy  on 

Dear All, I need to ensure that in the 60/60 rule, I do not find anything about the maximum indoor temperature during flush-out, please advice if I can maintain any indoor temperature as long as it

3
Green Building Consultant | Researcher
GreenA Consultants
LEEDuser Basic Member
38 thumbs up
Thu May 12, 2016, 12:21 pm

Purpose behind the 60% RH parameter?

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Landry Watson  on 

The reference guide is clear that 14,000 CFM of OA per SF (that is >60deg and

5
Assistant Vice President - Sustainability
Alexandria Real Estate Equities
LEEDuser Premium Member
26 thumbs up
Wed May 4, 2016, 11:56 pm

Path 2 Flushout

NC-2009 IEQc3.2:Construction IAQ management plan - before occupancy
posted by  Amy Harmon  on 

Our project went with Path 2 Post-occupancy flush out. All AHUs required 2-4 days of flush out before occupancy could occur and about 24 days post occupancy.

10
Founder & Community Director
Metricorps
LEEDuser Expert
7781 thumbs up
Wed May 4, 2016, 10:08 pm