Apparatus Bay Flush out
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Richard Naldrett on
We have a Fire Station project scheduled for a flush out of the Appratus Bay. The space has heating but there is not a simple way to control humidity.
IAQ Flush out-using temporary exhaust systems
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Stella Stella on
Hi, We are proposing a IAQ flush out procedure for our facility which consist of a lot of FCU’s. Due to the FCU’s the flush out procedure is excessively long.
Implementing IAQ testing shell space
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Summer Minchew on
Noting that an equivalent to IEQc3.2 is not available within the LEED-CS rating system, is it safe to assume that future tenant space(s) within a LEED-NC project would not be subject to IAQ testing
Air testing related to partial renovation per floor
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Julie Barth on
I have a client who is asking about air testing for an office building renovation project where small parts of each floor will be renovated.
Number of air testing samples
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Qian Tang on
Our project office building has 22 floors and is divided in 4 portions – north wing, south wing, east wing and west wing.
Questions.
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by ethen mcmanus on
Listed below is my list of questions: A) We have several FRESH air handling units and REGULAR air handling units on the roof of our building.
Combine options
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Leandro Silva on
We are certifying a Project and we are preparing the documentation for the EQ credit 3.2 Construction Indoor Air Quality Management Plan – Before Occupancy.
Maximum Temperature
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Omar Elrawy on
Dear All, I need to ensure that in the 60/60 rule, I do not find anything about the maximum indoor temperature during flush-out, please advice if I can maintain any indoor temperature as long as it
Purpose behind the 60% RH parameter?
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Landry Watson on
The reference guide is clear that 14,000 CFM of OA per SF (that is >60deg and
Path 2 Flushout
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Amy Harmon on
Our project went with Path 2 Post-occupancy flush out. All AHUs required 2-4 days of flush out before occupancy could occur and about 24 days post occupancy.