Forum quick links
Another CxA Scenario?
NC-2009 EAc3:Enhanced Commissioningposted by Christopher Heine on
We have a project over 50,000 sf in DD phase and are in early talks with a potential Facility Manager. Can a FM or a disinterested party from that FM firm serve as a CxA for EAc3?
Document review
NC-2009 EAc3:Enhanced Commissioningposted by Adam Rustige on
Is reviewing I&O manuals and as-built drawings a requirement for enhanced commissioning? Thanks
CxA also testing and balancing agent?
NC-2009 EAc3:Enhanced Commissioningposted by Maya Karkour on
Hello, "X" was appointed as third party CxA by the owner, since the start of the project.
smoke leakage test for duct
NC-2009 EAc3:Enhanced Commissioningposted by Abdulla Anwar on
Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test? prior to air leakage test since the project specs is giving a small allowable 1% from basis of design?
Signed Contract with the CxA
NC-2009 EAc3:Enhanced Commissioningposted by Mohamed M. Abd Elhameed on
We are pursuing LEED Certification for a 476921.20 sq ft Mixed Use Office Building in Egypt.
Major Change to Who Can Be a CxA!
NC-2009 EAc3:Enhanced Commissioningposted by Scott Bowman on
I was trying to do some catching up, and the July Addenda has a very significant change to who can be the CxA.
EAc3 - Enhanced Commissioning, LEED v2009
NC-2009 EAc3:Enhanced Commissioningposted by Jared Reed on
Our project is pursuing EAc3 - Enhanced Commissioning. The reference manual states that the CxA performing the enhanced commissioning must also perform the fundamental commissioning.
How to apply the enhanced commissioning task to existing?
NC-2009 EAc3:Enhanced Commissioningposted by Dave Hubka on
Hi Scott, We are involved with a major addition to an existing building. We will be certifying the entire building.
District Energy System owned by Government vs. Owner
NC-2009 EAc3:Enhanced Commissioningposted by Erin Holdenried on
My question is in regard to both EAc3: Enhanced Commissioning and EAc5: Measurement and Verification credits in relation to a District Energy System.
Timing of systems manuals
NC-2009 EAc3:Enhanced Commissioningposted by Melinda Shah on
The LEED NC multiple building project we are working on has been occupied for 6-18 months (depending on the building) and we have everything ready to submit everything for the construction review e